Corrective Actions
1 Investigate and remedy (see note 1):
2 Resize or redesign within Technical Databook
Guidelines. (If larger protection is required,
ensure supply cables are compatible).
3 a redesign for lower start-up temperatures
b  preheat pipe from alternative heat source to within expo-
sure temperatures given in Product
Data Sheets
c   Energize part of circuit followed by remainder
(e.g. in sequence
4 Replace
Corrective Actions
1 Investigate and remedy (see note 1):
2 Dry out and reseal or remake immediately.
Perform insulation resistance test.
(10 MΩ minimum)
3 Redesign
4 Redesign distribution, guidance is available from
nVent
5 Replace