Installation Guide

24 | nVent.com/RAYCHEM
4.3 Component installation hints
On horizontal pipes locate junction boxes below pipe
wherever possible. Pinch out drainhole in the stand when
installing upside down.
Locate junction boxes for easy access but not exposed to
mechanical abuse.
Position junction boxes so that power cable and heating
cable entries do not point upwards.
Figure 9a
JBS-100-L-EP
Integrated power connection
(with earth plate and light)
Fix lids in place where access not required.
Confirm junction box stopping plugs are correct for
application and fixed firmly in place.
Route heating cable from junction box to insulation entry so
as to avoid possible mechanical damage.
Do not strain heating cable as it exits/enters junction
boxes and insulation entries.
Ensure heating cable is fixed above pipe straps such as used
for junction box support brackets.
Fix all low profile components (e.g. heatshrink end seals) in
place with self-adhesive glass cloth tape.