User Manual
Setup and Configuration 6-41
Prompted Setup
Prompted Setup is generally the most frequently used setup procedure. It should be
performed prior to all production runs, after changing the needle or valve, and if you are
experiencing inaccurate dispensing.
?NOTE If you have a Dual-Action or a Dual-Bracket dispensing head, it is
recommended that you use the Scripted Prompted Setup described below.
To perform a Prompted Setup routine:
1. In the Main Window, click on Configuration.
2. Select Prompted Setup Options
Prompted Setup OptionsPrompted Setup Options
Prompted Setup Options from the Configuration menu.
> The Prompted Setup Options dialog box, shown in Figure 6-15, opens.
Figure 6-15
3. Select Non-Scripted Prompted Setup
Non-Scripted Prompted SetupNon-Scripted Prompted Setup
Non-Scripted Prompted Setup.
> Scripted Prompted Setup is described below in the next section.
4. Click on OK.
5. In the Main Window, click on Run a Program.