Manual
Start-up/Shutdown 5-7
Operator Shutdown/End of Shift in FMDOS
The following are recommended procedures for a production shutdown.
To shut down at the end of a shift:
1.
Wait for the dispensing program to complete.
2.
Press the Power Switch on the Control Panel
OFF
( ).
3.
Remove workpieces from the dispensing area.
4.
Remove the syringe from the dispense head.
5.
Clean or purge your fluid pump, refer to your Valve or Fluid Pump manual.
Service Shutdown in FMW
Use the following recommended procedures to shutdown the Century Series System for
service or moving. This procedure is for service technicians only.
To shut down for service:
1.
End your dispensing program in FMW.
Click
from the Run Window screen.
Click from the Production Window screen.
Click
from the Main Window screen
2.
Remove the syringe from the dispense head.
3.
Remove workpieces from the dispensing area.
4.
Clean or purge your fluid pump.
5.
Press the Power Switch on the Control Panel OFF ( ).
6.
Press the Main Power Switch on the rear of the Century Series system
OFF
( ).
7.
Unplug the Main Power Plug.
8.
Remove the air supply by disconnecting your air source from Main Air In.
9.
Perform service, as necessary.