Installation Manual

5-36 Power-up and Testing
Lift Table and Heater Tooling Leveling
If your dispensing system is equipped with Lift Tables, perform the following procedure to make sure that
they are level.
? NOTE This procedure assumes that each Lift Table is equipped with Heater Tooling and that
the Height Sensor has been functionally tested.
1. In the FmNT Main Window, click on the
Configuration button and select Setup
Height Sensor
.
2. In the Height Sensor Configuration dialog box, click on
CAN-HS. See Figure 5-10.
3. In the second Height Sensor Configuration dialog box, click on the
ARM/DISARM button
until the “Current Arm State” reads
ARMED.
> The Height Sensor Probe should be in the down position.
4. Click on
OK twice to return to the Main Window.
5. In the FmNT Main Window, click on
Configuration and then select Setup Conveyors.
6. In the Setup Conveyors dialog box, click on the
Test I/O button. See Figure 5-9.
7. In the MPC555 I/O Diagnostic dialog box, select the
Station I/O Diagnostic tab.
8. In the Station I/O Diagnostic dialog box, click on the dispense station
Clamp/Lifter button to
raise the Lift Table and Heater Tooling. See Figure 5-9.
9. Click on
OK twice to return to the Main Window.
10. In the Main Window, click on the
Jog icon .
11. In the Jog Commands dialog box, click on
Conveyor. See Figure 5-14.
12. Click on
Home in the Jog Commands dialog box to make the rear Conveyor Rail moves to
the home position at the rear of the dispensing chamber.
13. In the Jog Commands dialog box, click on
Dispenser. See Figure 5-11.
14. Using the Dispenser XY position controls, move the Height Sensor Probe over one corner of
the Heater Tooling. See Figure 5-19 for approximate location.
CAUTION! Avoid contacting Board Sensors or other components attached to the
Conveyor Rail.
15. Using the Z-axis position controls, lower the Dispensing Head toward the top of the Heater
Tooling until the green LED on the Height Sensor illuminates.
> Measurements are taken on top of the Heater Tooling because if the top of the Heater
Tooling is level, it is assumed that the top of the Lift Table is also level.