Installation Manual
X-1000 Installation Checklist
10 of 13
Step
#
Done
(9)
Test Performed Main Function(s) Tested
56.
Tooling Heaters
Verify that the Conveyor heater terminal
window comes up without any errors
FMNT-CAN
57. Verify that the heaters ramp up to
temperature (50 °C) within 5 minutes.
Using an external heater probe:
Verify that the heaters are heating to the set
point temperature.
Change set point to 140 °C and verify that
they reach this temp within another 10
minutes. Verify that they also stabilize and
maintain this temperature.
Temp control, wiring
58. Verify that each channel begins to ramp
down (5 degrees) when heaters are turned
off.
Temp control, wiring
59.
Verify that all station timers work properly Conveyor CAN-FMNT