Installation Manual

Troubleshooting 8-117
13. Verify continuity of the SMEMA Downstream Cable (P/N 06-4644-00), routed between Conveyor
Controller and the Rear Bulkhead of the dispensing system. Pin connections are specified in
Table 8-35.
Table 8-35 SMEMA Downstream Cable Pin Connections
P1 Color P2
1BlackN/C
2White 1
3 Red 10
4 Green 2
5Brown12
6Blue 4
7 Orange 11
8Yellow 9
9Purple 3
Shell Shield 8
14. Is there continuity?
SMEMA Downstream Cable (P/N 06-4644-00) has
failed. See
Parts Replacement section.
Go to Step 15
15. Connect the Power Cable to the facility outlet, switch Main Circuit Breaker to ON (I) position, press
the green
ON (I) button on the Operator’s Console, and enter FmNT.
16. Press Button 5 on the TS-01 Box.
17. In the FmNT I/O SMEMA screen, verify that “Board available from downstream tool” is
displaying ON.
18. Is ON displayed?
Go to Step 19
External SMEMA Downstream Cable (P/N 06-2141-00), or Downstream
System has failed. See
Parts Replacement section for the cable.
19. Exit FmNT, shut down Windows NT, press the black OFF (0) button on the Operator’s Console,
switch Main Circuit Breaker to
OFF (0) position, and disconnect Power Cable from the facility outlet.
No
Yes
No
Yes