Installation Manual

Troubleshooting 8-113
Upstream Workpiece Transfer Verification
1. Exit FmNT, shut down Windows NT, press the black
OFF (0) button on the Operator’s Console,
switch Main Circuit Breaker to
OFF (0) position, and disconnect Power Cable from the facility outlet.
2. Connect the TS-03 Kit to the SMEMA upstream and downstream connectors.
3. Connect the Power Cable to the facility outlet, switch Main Circuit Breaker to
ON (I) position, press
the green
ON (I) button on the Operator’s Console, and enter FmNT.
4. In the FmNT I/O SMEMA screen, click
Request board from upstream tool.
5. Did LED 2 on the TS-01 Box illuminate?
Go to Step 6
Go to Step 16
6. Exit FmNT, shut down Windows NT, press the black OFF (0) button on the Operator’s Console,
switch Main Circuit Breaker to
OFF (0) position, and disconnect Power Cable from the facility outlet.
7. Remove the Side Cover from the Conveyor Controller.
8. Connect the Power Cable to the facility outlet, switch Main Circuit Breaker to
ON (I) position, press
the green
ON (I) button on the Operator’s Console, and enter FmNT.
9. In the FmNT I/O SMEMA screen, click
Request board from upstream tool.
10. Locate the four SMEMA LEDs near the top of the Conveyor Interface PWA (just right of center).
11. Is LED D24 illuminated?
Conveyor Controller (P/N 62-1677-00 on X-1020, or
P/N 62-1676 on X-1010) has failed. See
Parts
Replacement
section.
Go to Step 12
12. Exit FmNT, shut down Windows NT, press the black OFF (0) button on the Operator’s Console,
switch Main Circuit Breaker to
OFF (0) position, and disconnect Power Cable from the facility outlet.
No