5-48 Power-up and Testing
3. Once you have completed the Valve Offsets or Scripted Valve Offsets routine, perform a
simulated (dry) production run using the TS-01 Test Box as follows:
? NOTE If your system has Heat Tooling, make sure the Heaters have reached the set
point (SP) before proceeding with this procedure.
a. Perform a Service Shutdown as specified in the Safety section of this manual.
b. Attach the TS-01 upstream and downstream cable adapters to the TS-01 I/O Test Box.
See Figure 5-16.
c. Attach the TS-01 upstream and downstream cables to the appropriate SMEMA
connectors at the rear of the dispensing system.
d. Perform a Post-Service Start-up as specified in the Safety section of this manual.
e. Make sure that all of the
I↔
↔↔
↔O/INDEP switches along the edge of the TS-01 I/O Test Box
are all set to
INDEP.
f. Make sure that the
DRIVERS/OPTO I/O switch in the corner of the TS-01 I/O Test Box is
set to
OPTO I/O.
g. In the FmNT Main Window, click on
Run a Program.
h. In the Production Window, click on
Load.
i. Select a dispensing program from the list and click on
Open. See Figure 5-25.
> A dialog box opens that says “Downloading <filename>…please wait.”
> The program will load and return you to the Production Window where the filename
of the program you selected should appear in the upper left.
Figure 5-25 Program Open Window