Installation Manual
Power-up and Testing 5-47
System-Level Functional Test
CAUTION! Provide a means to catch workpieces/carriers exiting the dispensing system or
they will fall on the floor and be damaged.
? NOTE This procedure assumes that a production program has been created in accordance with
the FmNT User Guide.
1. If applicable to your system, turn on the Heat Tooling as follows (see Figure 5-20):
a. In the FmNT Main Window, click on
Tools.
b. In the Tools Window, click on
Terminal.
c. Click on
Heaters.
d. In the Heater Control Window, locate the loops (channels) for the Heater Tooling
installed on your system.
2. Perform a Valve Offsets routine as follows (see Figure 5-24):
a. In the FmNT Main Window, click on
Configuration.
b. Select
Machine Offsets from the Configuration menu.
c. In the dropdown menu, select
Machine Offsets Parameters.
d. In the Machine Offsets Parameters dialog box, select
Valve Offsets or Scripted Valve
Offsets
and click on OK.
> Follow the prompts to perform the routine. Consult FmNT Online Help for
instructions, if necessary.
Figure 5-24 Valve Offset Dialog Boxes
As
y
mtek FmNT – Main Window