Cross-connections
DN999099 © Nokia Corporation Draft 69 (78)
Issue 4-0 en Nokia Proprietary and Confidential
7. Click the NEXT button in the wizard to open the TX2/RX2 dialogue box.
8. Select the next interface, such as Interface 2.
9. Define the settings for this second interface and click NEXT.
10. The Overview dialogue box will open. Depending on the type of cross-
connection, various fields will be enabled for defining the cross-connection
parameters according to your cross-connection plan. For more information
on the parameters, see the on-line Help in E1/T1 Manager.
Click FINISH.
11. The Add Cross-connection Wizard will close and you will return to the
Cross-connections window. The new cross-connection appears in the list
in the upper part of the window.
12. Activate the bank by clicking the ‘Banks’ ACTIVATE button. Click YES
when the E1/T1 manager asks you to confirm the operation.
13. Repeat Steps 1 - 12 for other types of cross-connections.
14. Quit the transmission unit manager by clicking the CLOSE button. Nokia
BTS Manager starts again automatically.
Editing a bank
You can start to edit existing settings in an inactive bank by double-clicking the
particular connection in the cross-connection list view in the Cross-connection
window or by selecting the connection and choosing the EDIT command on the
pop-up menu (which appears when you right-click the mouse).
If you have activated the bank, you need to copy the cross-connection information
to the inactive bank for editing because active banks cannot be edited. The COPY
command also is available in the pop-up menu.