Product Info
Table Of Contents
- Field Upgrade
- 1 Overview of field upgrade
- 2 Preparing for upgrade
- 3 Replacing the power supply unit
- 4 Replacing the cooling fan
- 5 Replacing or installing new TRX units
- 6 Chaining Nokia MetroSite EDGE BTSs
- 7 Commissioning for upgrade
- 8 Completing the upgrade
Commissioning for upgrade
DN00187365 © Nokia Corporation Draft 43 (50)
Issue 2-0 en Nokia Proprietary and Confidential
Note
Note
Note
4. Start BTS Manager 3.0 on your laptop.
5. With BTS Manager, uncommission the master BTS by selecting
COMMISSIONING | WIZARD from the main menu and selecting the
‘Undo Commissioning’ button.
Before or during the commissioning of the BTS chain, CX 3.0 software must be
loaded to the master BTS from the BSC. CX 3.0 software or later must be
available at the BSC.
The newly chained BTS site should remain in the locked state until you have
completed the commissioning procedures. Do not request a BCF unlock until you
have commissioned the BTS chain.
6. Carry out the commissioning process with BTS Manager’s Commissioning
Wizard, as described in the document Nokia MetroSite EDGE Base
Station: Commissioning. At the stage of traffic allocation, follow the
instructions called Allocating transmission capacity for chaining in the
Traffic Manager chapter of the document.
It is important that when commissioning has been completed, the new BTS are
unlocked in the BSC database before the BCF is unlocked.
7. When commissioning is complete, disconnect the laptop from the master
BTS and carry out the procedures in Chapter 8 of this document,
Completing the upgrade.