Access P oint Hardw are Installation Installation Completion Checklist
Table 6 -1 Hardw are Installation Checklist
Item
No.
Item Notes
1
Equipment is not damaged.
2
Air flow clearance requirements are met.
3
Base Control Unit (B CU) is securely mounted to wall
or pole.
4
B CU and RF Carrier Unit (RFCU) are RF cabled
correctly .
5
B CU and RFCU are DC power cabled correctly .
6
B CU is ethernet cabled. (If installed)
7
RF Head is securely mounted to pole.
8
Band P ass filters are cabled to RFCU correctly (If
used)
9
Conduit is sufficiently grounded
10
Antennas are grounded to tower
11
The antenna cables are protected by lightning
arrestors (if applicable).
12
B CU is grounded
13
RF Head is grounded.
14
RGPS is cabled to B CU .
15
RGPS head and mast are secure.
16
RGPS connection is protected by lightning arrestors
(if applicable).
17
RGPS head has a clear view of the sky and is not in a
location which accumulates debris. Make sure the
RGPS is located away from the transmit antennas.
18
Local GPS (RF GPS) antenna is secure. (If used)
19
Local GPS cabling is installed (If used).
20
Installation hardware is removed.
21
The site is cleaned, swept and trash removed.
22
The site specific documentation is present at the site.
68P09277A59 -8 6 -5