User's Manual

Access P oint Hardw are Installation Prepare Site for Equipment Arriv al
Prepare Site for Equipment Arrival
Description
This information covers various topics not all of which are needed at every site. Based on the
site characteristics execute the steps that apply to your site. Before installing the equipment, do
the following to ensure the safety of installation personnel and to protect the equipment.
Equipment Arrival
Before the equipment arrives, indicate to the transport company an area at the site where the
equipment can be unloaded and, if necessary , unpacked. The equipment should be carefully
delivered to the site, along with all equipment dollies and padding required to safely move the
equipment from the unloading area to the cell site. The following should also be provided,
outdoor weather protection, temporary lighting and power for lighting and power tools.
Procedure to Prepare the Site for the Equipment
Procedure 2 -1 Procedure to Prepare the Site for the B T S
1
Consult with site manager .
2
Locate the demarcation blocks for external utilities.
V erify that they are shown on the Site Engineering documents, and
determine the required cable routing back to the equipment frames.
3
V erify the following:
AC power is available and meets the site documentation specifications
P ole and/or wall mounting structures are adequate
Outdoor cable runs are installed and meet local building codes
Customer input termination tie points are available
There is clear access to move the equipment to the desired mounting
area
There is sufficient space for installation and service access to the
equipment
Customer supplied shelters are installed
68P09277A59 -8 2 -3
PRELIMINARY - UNDER DEVELOPMENT MA Y 2007