Product Info
Table Of Contents
- 13.1_IHET6HG1_install_manual.pdf
- Install_Manual_PRELIMINARY
- R20 1X UBS Macro BTS Hardware Installation
- Copyrights
- Contents
- List of Figures
- List of Table
- About This Manual
- Front Matter
- Chapter 1 - Introduction and Frame Identification
- Abbreviations and Acronyms
- Overview
- Scope of manual
- Prerequisites
- Chapter 1 - Introduction and frame identification
- Chapter 2 – UBS Macro BTS installation procedure
- Chapter 3 - Low-to-Mid Capacity Frame Expansion Procedures
- Chapter 4 - What’s next
- Equipment shipped assembled
- Equipment shipped un-assembled
- Follow the task sequence
- Follow the site plan
- Site cleanliness
- Site manager
- Color coding
- Rack vs. frame
- Required documentation
- Equipment may vary from figures
- Item identification
- UBS Macro BTS frames
- Figure 1-1 UBS Macro BTS low-tier/low-capacity frame (1000 mm ra
- Figure 1-2 Low capacity UBS Macro BTS starter frame (1800 mm rac
- Figure 1-3 UBS Macro BTS mid-capacity frame (1800 mm rack)
- Figure 1-4 High capacity 800 MHz UBS Macro BTS fully expanded fr
- Figure 1-5 High-capacity 1.9 GHz UBS Macro BTS fully expanded fr
- Items to be installed
- UBS Macro BTS frames
- Tools and materials
- Unpacking Instructions
- Chapter 2 - UBS Macro BTS Installation Procedure
Unpacking Instructions Chapter 1: Introduction and Fr ame Identication
Unpacking Instructions
■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■
■
■
Unpacking the carrier strip assembly
The UBS Macro BTS carrier strip assembly includes the low -capacity frame equipment
pre -mounted and cabled. This assembly consists of the following equipment:
• One set of IDRFs, up to three IDRFs.
• One S SI
• One XMI
• One DMI
• PDU with one +27 V DC input power feed and circuit breaker/output power connector
assemblies as follows: XMI 1, DMI 1, DMI 2 and S SI 1.
The STGN4034 Installation Kit is also packaged with the UBS Macro carrier strip
assembly . The installation kit contains all of the M5 x 12 mm screws needed to rack
mount the equipment.
The UBS Macro BTS carrier strip assembly is shipped in a large carton that is banded to a pallet.
F ollow the steps in Procedure 1 -1 to unpack the carrier strip assembly .
Procedure 1 -1 Unpacking the carrier strip assembly
1
Cut the bands that hold the carton to the pallet.
2
Lift the carton up and off of the pallet. Remove the cut bands
3
Remove the inner carton support (see Figure 1-7 ).
The carrier strip assembly is sitting on a wooden support (see
Figure 1-8 ).
4
Locate the STGN4034 Installation Kit that is packaged with the UBS Macro
carrier strip assembly .
5
Inspect the carrier strip assembly for damage.
1 -18 68P09283A62 -2