User's Manual

RFDS Set–up and Calibration – continued
FEB 2005 1X SC 4812T Lite BTS Optimization/ATP 3-139
PRELIMINARY
Table 3-51: RFDS Calibration Procedure
n ActionStep
10 Click on the OK Button.
A Status Report Window is displayed, followed by a Directions Pop–up Window.
11 Follow the Cable Connection Directions as they are displayed.
12 When the test is completed, the test results are displayed in the Status Report Window.
13 Click on the OK Button to close the Status Report Window.
14 Click on the BTS Frame Tab.
15 Select the MGLI by clicking on it.
16 Download updated RFDS offset data to the MGLI.
Refer to Step 5 in Table 3-45.
TSU Program TSU NAM
The NAM must be programmed before it can receive and process Test
Calls, or be used for any type of RFDS Test.
Prerequisites
S MGLI is INS_ACTIVE (bright green).
S SUA is powered up and has a Code Load.
Perform the procedure in Table 3-52 to program the TSU NAM.
Table 3-52: Program TSU NAM Procedure
n Step Action
1 In the LMF, select the RFDS Tab.
2 Select the SUA by clicking on it.
3 Click on TSU in the BTS Menu Bar, and select Program TSU NAM from the Pull–down Menu.
A NAM programming window will appear.
4 Enter the appropriate information in the boxes. Refer to Table 3-46 and Table 3-47) .
5 Click on the OK Button to display the Status Report.
6 Click on the OK Button to close the Status Report Window.
3