User's Manual

Table Of Contents
Acceptance Tests – Test Set–up
4-4 1X SC 4812T Lite BTS Optimization/ATP FEB 2005
PRELIMINARY
Required Test Equipment
The following Test Equipment is required:
S LMF
S Power Meter (used with HP 8921A/600 and Advantest R3465)
S Communications System Analyzer
S Signal Generator for FER Testing (required for all Communications
System Analyzers for 1X FER)
Before installing any Test Equipment directly to any
BTS TX OUT Connector, verify that there are no
CDMA Channels keyed.
At active sites, have the OMC–R/CBSC place the
carrier assigned to the LPA Modules under test OOS.
Failure to do so can result in serious personal injury
and/or equipment damage.
WARNING
The Test Equipment must be re–calibrated before using it
to perform the TX Acceptance Tests.
NOTE
Acceptance Test Equipment
Set–up
All ATP Testing
Perform the procedure in Table 4-1 to Set–up Test Equipment for all
tests..
4