Prepare to Leave the Site – continued
FEB 2005 1X SC 4812T Lite BTS Optimization/ATP 5-7
PRELIMINARY
Table 5-6: Circuit Backhaul Remote Reset and Initialization Procedure
n ActionStep
10 Once the GLI Cards are loaded with the specified Code Version, the active GLI will verify and
update, as required, its RAM.
Also, if necessary, ROM Code Loads for the installed CSM, MCC, and BBX Cards using the
DLM.
11 After all activities at the site have been completed, contact the OMC–R to confirm that the BTS is
under OMC–R control.
Packet Backhaul Remote Reset and Initialization
Perform the procedure in Table 5-7 to remotely reset the BTS Devices in
a Packet Backhaul BTS, and then remotely initialize the same BTS.
Table 5-7: Packet Backhaul Remote Reset and Initialization Procedure
n Step Action
1 Terminate the LMF Session by performing the procedure in Table 5-3.
2 Reconnect the Spans by performing the procedure in Table 5-4.
3 Determine which of the two types of PREACTIVATE Load Processes is applicable to your
situation.
Rolling Upgrade: This Load Process is only available when the BTS Cards are populated for Full
Redundancy as applicable.
Quick Reboot: This Load Process is used when Redundancy for the BTS Cards is not available.
The GLI3 disables and reboots to the new Load. This will cause all the other cards to go out
of service.
Once it is rebooted, the GLI3 determines which cards require a new Load and then downloads
the cards in the order that they establish communication with the GLI3 following their reboot.
The GLI3 can reload up to 16 devices simultaneously.
4 From the BTS Site, contact the OMC–R and request the operator to PREACTIVATE the BTS to
the required software version for the BSS.
5 After all activities at the site have been completed, contact the OMC–R to confirm that the BTS is
under OMC–R control.
5