User Manual

Initializing Active Service68P09255A57-2
Aug 2002
SC4812ET Optimization/ATP Manual Software Release R16.1.x.x
PRELIMINARY
5-7
Table 5-5: Set BTS Span Parameter Configuration
Step Action
5 This completes the site specific BTS Span setup for this GLI. Move the MMI cable to the next SGLI3
and repeat steps 1 and 4 for ALL MGLI3/SGLI3 boards.
6 Terminate the Hyperterm session and disconnect the LMF from the MGLI/SGLI.
Re-connect BTS T1 Spans and Integrated Frame Modem
Before leaving the site, connect any T1 span TELCO connectors which
were removed to allow the LMF to control the BTS. Refer to Table 5-6.
Table 5-6: T1/E1 Span/IFM Connections
Step Action
1 Connect the surge protectors on the 50-pin punch block for the spans.
2 Ensure that the CSU is powered ON.
3 Verify the span status.
LMF Removal
CAUTION
DO NOT power down the CDMA LMF without performing the
procedure indicated below. Corrupted/lost data files may result,
and in some cases, the CDMA LMF may lock up.
Follow the procedures in Table 5-7 to terminate the LMF session and
remove the terminal.
Table 5-7: Terminate the LMF Session and Remove the LMF
Step Action
1 From the CDMA window select File>Exit.
2 From the Windows Task Bar click Start>Shutdown. Click Yes when the Shut Down Windows
message appears.
3 Disconnect the LMF terminal Ethernet connector from the BTS cabinet.
4 Disconnect the LMF serial port, the RS-232 to GPIB interface box, and the GPIB cables as required
for equipment transport.
Reestablish OMC-R Control/ Verifying T1/E1
NOTE
After all activities at the site have been completed, including
disconnecting the LMF, place a phone call to the OMC-R and
request the BTS be placed under control of the OMC-R.
5