Prepare Site for the Arrival of the Equipment – continued
DRAFT
1X SC480 BTS Hardware Installation, Optimization/ATP, and FRU
Jun 2004
2-6
Procedure to Prepare the Site
for the Equipment
Table 2-1: Procedure to Prepare the Site for the BTS
Step Action
1 If some type of protective padding is available install it around any existing equipment at the site that
could be damaged during installation of the unit(s).
2 Hang plastic sheets around intended work areas to prevent dust and debris from damaging co-located
equipment during installation.
3 Secure any fluorescent tubes in place using masking tape. (Refer to Figure 2-1.)
NOTE
This will prevent the tubes from being inadvertently jarred from the fixtures during the installation of
equipment or cables.
4 Locate the demarcation blocks for external utilities.
Verify that they are shown on the Site Engineering documents, and determine the required cable
routing back to the equipment frames.
5 Verify the following:
S DC power is available and meets the site documentation specifications (if applicable).
S Cable rack is installed per site document specifications.
S Outdoor cable runs are installed and meet local building codes.
S Span line termination tie points are available.
S Customer input termination tie points are available.
S There is clear access to move the equipment to the desired mounting area.
S There is sufficient space for installation and service access to the equipment.
S Customer supplied shelters are installed.