User Manual

Transmit & Receive Antenna VSWR
5/21/04 1X SC4812T–MC BTS Optimization/ATP G-1
DRAFT
Purpose
The following procedures will verify that the Voltage Standing Wave
Ratio (VSWR) of all antennas and associated feed lines fall within
acceptable limits. The tests will be performed on all antennas in a
sequential manner (i.e., ANT 1, then ANT 2) until all antennas/feedlines
have been verified.
These procedures should be performed periodically by measuring each
respective antenna’s VSWR (reflected power) to verify that the antenna
system is within acceptable limits. This will ensure continued peak
system performance.
The antenna VSWR will be calculated at the CDMA carrier frequency
assigned to each antenna. Record and verify that they meet the test
specification of less than or equal to 1.5:1.
Motorola recommends that the installer be familiar with
the following procedure in its entirety before beginning the
actual procedure. Ensure that the entire site is currently not
in service.
This test is used to test RX antennas by substituting RX
frequencies for TX frequencies.
NOTE
Study the site engineering documents and perform the following tests
only after first verifying that the RF cabling configuration required to
interconnect the BTS frames and antennas meet requirements called out
in the BTS Installation Manual.
Test equipment
The following pieces of test equipment will be required to perform this
test:
S LMF
S Directional coupler
S Communications test set
Prior to performing antenna tests, insure that no CDMA
BBX channels are keyed. Failure to do so could result in
personal injury or serious equipment damage.
WARNING
Equipment Setup – HP Test Set
Follow the procedure in Table G-1 to set up test equipment required to
measure and calculate the VSWR for each antenna.
G