User Manual
Initial Power Up Tests & Procedures
5/21/04 1X SC4812T–MC BTS Optimization/ATP 2-5
DRAFT
Power-up Procedures
Potentially lethal voltage and current levels are routed to
the BTS equipment. This test must be performed with a
second person present, acting in a safety role. Remove all
rings, jewelry, and wrist watches prior to beginning this
test.
WARNING
DC Input Power
In the tests to follow, power will first be verified at the input to each
BTS frame. After power is verified, cards and modules within the frame
itself will be powered up and verified one at a time.
Before applying any power, verify the correct power feed and return
cables are connected between the power supply breakers and the power
connectors at the top of each BTS frame. Verify correct cable position
referring to Figure 2-3.
NOTE
For positive power applications (+27 V):
S The positive power cable is red.
S The negative power cable is black.
For negative power applications (–48 V):
S The negative power cable is red or blue.
S The positive power cable (ground) is black.
Motorola recommends that the DC input power cable used to connect the
frame to the main DC power source conforms to the guidelines outlined
in Table 2-3.
Table 2-3: DC Input Power Cable Guidelines
Maximum Cable Length Wire Size
30.38 m (100 ft) 107 mm
2
(AWG #4/0)
54.864 m (180 ft) 185 mm
2
(350 kcmil)
Greater that 54.864 m (180 ft) Not recommended
Make sure the connector adapters are securely attached to
each of the BTS power feeds and returns. Also, make sure
the cables have been properly installed into each
connector.
NOTE
2