User Manual
Automated Acceptance Test Procedures – TX & RX – continued
5/21/04 1X SC4812T–MC BTS Optimization/ATP 4-3
DRAFT
ATP Test Prerequisites
All PAs must be INS during any TX testing.
NOTE
Before attempting to run any ATP tests, ensure the following have been
completed:
S BTS has been optimized and calibrated (see Chapter 3).
S LMF is logged into the BTS.
S CSMs, GLIs, BBXs, and MCCs have correct code load and data load.
S Primary CSM, GLI, and MCCs are INS_ACT (bright green).
S BBXs are calibrated and BLOs are downloaded.
S No BBXs are keyed (transmitting).
S BBXs are OOS_RAM (flashing green).
S Test cables are calibrated.
S Test equipment is connected for ATP tests (see Figure 3-18 through
Figure 3-23).
S Test equipment has been warmed up 60 minutes and calibrated.
S GPIB is on.
S BTS transmit connectors are properly terminated for the test(s) to be
performed.
Before performing the FER, be sure that all PAs are turned
OFF (circuit breakers pulled) or that all transmitter ports
are properly terminated.
All transmit ports must be properly terminated for all ATP
tests.
Failure to observe these warnings may result in bodily
injury or equipment damage.
WARNING
TX OUT Connection
Many of the acceptance test procedures require taking
measurements at the TX OUT connector. All
measurements will be via the BTS TX OUT connector.
NOTE
4