Prerequisites
Before attempting to run any ATP tests, all applicable procedures
outlined in Chapter 3, Optimization/Calibration, must have been
completed successfully (i.e., code load and BLO calibration).
You cannot substitute test equipment with other models not
supported by the CDMA LMF.
NOTE
Before attempting to run any ATP tests, ensure the following:
S BTS has been optimized and calibrated (see Chapter 3).
S LMF is logged into the BTS
S CSMs, GLI2s, BBX2s, MCCs and TSU (if the RFDS is installed)
have correct code load and data load
S Primary CSM and GLI2 are INS_ACT
S MCCs are INS_ACT
S BBX2s are OOS-RAM
S BBX2s are calibrated and BLOs are downloaded
S Test cables are calibrated
S Test equipment is selected
S Test equipment is connected for ATP tests
S Test equipment has been warmed up 60 minutes and calibrated
S GPIB is on
Before the FER is run, be sure that all LPAs are turned
OFF (circuit breakers pulled) or that all transmitter
connectors are properly terminated.
All transmit connectors must be properly terminated for all
ATP tests.
Failure to observe these warnings may result in bodily
injury or equipment damage.
WARNING
TX/RX Antenna Connections
Refer to Figure 1-6 or Figure 1-7 for identification of the transmit and
receive antenna connections where measurement are to be taken.
Directional couplers for signal sampling by the RFDS, if installed, are
integral to the SC4812ET Lite transmit and receive paths in the DRDCs
and TRDCs. As a result, all ATP measurement connections are made at
the antenna connectors on the RF interface panel.
4