BTS Redundancy/Alarm Testing – continued
DRAFT
SCt4812T CDMA BTS Optimization/ATP
Mar 2001
3-86
68P09253A61
Test Equipment Setup
Follow the procedure in Table 3-46 to set up test equipment:
All alarm tests are performed using TX antenna 1
NOTE
Table 3-46: Test Equipment Setup for Redundancy/Alarm Tests
Step Action
1 Interface the LMF computer to the BTS LAN A connector on the BTS frame (refer to Table 3-2,
page 3-5).
2 Login to the BTS.
3 Set up test equipment for TX Calibration at TXOUT1 (see Figure 3-11 or Figure 3-12).
* IMPORTANT
If site is not equipped for redundancy, remove all GLI2 and BBX boards installed in any redundant
slot positions at this time.
4 Display the alarm monitor by selecting Util>Alarm Monitor.
5 Unequip all customer defined AMR alarms reported via the AMR Alarm connector (A & B) by
clicking on MGLI, then selecting Device>Customer Alarm Inputs>Unequipped.
NOTE
During configuration of MGLI alarm reporting, spurious alarms may report. Allow the BTS to
stabilize for 10 seconds. If any alarms are actively being reported after the BTS has stabilized,
determine the cause before proceeding further.