Table 4-6 reviews the procedure to install a string of batteries in the
Power Cabinet (see Figure 4-5 and Figure 4-6), this procedure should be
repeated until all battery strings have been installed.
Heater pads must be installed and heater pad cables
properly dressed behind battery shelves before batteries are
installed.
CAUTION
Do not install the batteries until the Power Cabinet has
been bolted down.
NOTE
Table 4-6: Installing a String of Batteries
Step Action
1 Remove battery mounting bracket (see Figure 4-6) from the shelf.
2 Install each battery into its slot, and slide the battery all the way into
the cabinet, ensure that the battery terminals face forward.
n WARNING
Use care when handling batteries, as they can weigh up to 48 kg (105
lbs). Do NOT drop the batteries.
3 Replace the battery mounting brackets, and torque the nuts to 5 Nm
(45 inlbs) with a 10 mm driver.
Figure 4-5: Typical 12V Battery
Power Cabinet Battery Cabling
The objective of this procedure is to install the Power Cabinet battery
connections. The quantity of batteries installed depends on the system
configuration. This section will detail the installation of a string of
batteries, this should be repeated until all battery strings have been
installed.
. . . continued on next page