Check that all FRU modules and doors are closed and latched.
Organize any items (manuals, materials, etc.) left on site and place
them in a location specified by the site manager.
Fill out Installation Completion
Checklist
After the site is cleaned up, fill out the installation completion checklist
(see Table 6-1) and make any necessary copies. Make copies of this
checklist as needed.
Date Hardware Installation Completed:
Site:
Master BTS Cabinet Serial Number(s):
Expansion BTS Cabinet Serial Number(s):
Checklist Completed By:
Checklist Reviewed By:
Table 6-1: Installation Completion Checklist
Status No. Item Notes
1 Cabinets are bolted down with mounting bolts
properly torqued.
2 Each cabinet has its own earth ground that is
connected to a proper site grounding system.
Ground MUST be connected first.
3 AC power cabling completed and checked by an
electrician and the AC breakers are OFF.
4 DC power cabling between Power and RF cabinets
is installed and the DC breakers are OFF.
5 Battery breakers are OFF.
6 RX RF cables installed.
7 TX RF cables installed.
8 RF connections are properly sealed with tape.
9 Span and Modem line cables installed.
10 RF cabinet alarm cable is installed.
. . . continued on next page