Installation Instructions
Test Equipment Setup
DEC 2000
7-29
SCt300 BTS Hardware Installation, ATP and FRU Procedures
PRELIMINARY
Purpose
The following test equipment setup applies to the BTS Acceptance Test
Procedure (ATP).
Required Test Equipment
The following pieces of test equipment will be required to perform these
ATP tests:
S LMF
S Power Meter
S Communications Test Set
To prevent damage to the test equipment, all Microcell
transmit (TX) tests must be made using the 30 dB
attenuator.
CAUTION
Test Set Calibration
Background
Proper test equipment calibration ensures that the test equipment and
associated test cables do not introduce measurement errors, and that
measurements are correct.
If the test set being used to interface with the BTS has been
calibrated and maintained as a set, this procedure does not
need to be performed. (Test Set includes LMF terminal,
communications test set, additional test equipment,
associated test cables, and adapters.)
NOTE
This procedure must be performed prior to beginning the optimization.
Verify all test equipment (including all associated test cables and
adapters actually used to interface all test equipment and the BTS) has
been calibrated and maintained as a set.
If any piece of test equipment, test cable, or RF adapter,
that makes up the calibrated test equipment set, has been
replaced, re-calibration must be performed. Failure to do so
can introduce measurement errors, resulting in incorrect
measurements and degradation to system performance.
CAUTION
7