Installation Instructions

Unit Installation Overview
DEC 2000
6-1
SCt300 BTS Hardware Installation, ATP and FRU Procedures
PRELIMINARY
Overview
This chapter provides the procedures for unit installation and cabling.
The site cabling has been installed and routed to the location of the BTS.
In this chapter, the cables will be attached to the unit(s). Cabling
installation will be repeated as necessary for each unit at the BTS.
This chapter provides the information and procedures to:
S Attach the unit to the mounting bracket
S Attach cables to the unit
S Power on the unit
S Mount the solar covers
S Complete the installation completion checklist
Unit Installation Procedure
Order
The process of installing the unit requires that the following procedures
be completed in the order shown:
1. Attaching fin covers to the unit – optional
2. Attaching the installation handles to the unit
3. Attaching the unit to the mounting bracket and removing the
installation handles
4. Attaching earth ground cable and optional master ground cable.
5. Attaching the Site I/O junction box to the unit
6. Attaching the short duration battery (optional)
7. Attaching the AC input power or DC input power cable
8. Attaching antenna cable(s)
9. Attaching the MIB cables (optional)
10. Attaching the SU cables (optional)
11. Terminating unused connectors
12. Powering on the unit
13. Mounting solar cover
14. Cleaning up site
15. Filling out the installation completion checklist