Installation Instructions
TX Acceptance Tests
PRELIMINARY
SCt300 BTS Hardware Installation, ATP and FRU Procedures
DEC 2000
8-8
TX ATP Test
Refer to Table 8-3 to perform a TX ATP test. This procedure assumes
that the site specific CDF file is in the wlmf\cdma\bts–# folder.
The ALL TX list performs the following ATP tests:
1. TX Mask
2. Rho
3. Pilot Time Offset
4. Code Domain Power
Prerequisites
Before attempting to run an ATP, all procedures outlined in previous
chapters should have been successfully completed.
Table 8-3: TX Acceptance Test Outline
Step Action
1 Set up test equipment for TX tests per NO TAG.
2 Perform the following to run TX Acceptance Tests:
– Select the MAWI.
– Click on the Tests menu
– Select ALL TX.
* IMPORTANT
The DPLL must be tracking either GPS or HSO.
TX Tests Using Backup
Synchronization (Sites
Equipped With GPS)
Follow the steps in Table 8-4 to perform the TX test using backup
synchronization.
Table 8-4: TX Test Using Backup Synchronization
Step Action
1 If logged into the BTS with the LMF, then logout.
2 Open an MMI Communication session.
3 Verify that the BTS is in OOS_RAM status by entering the status command.
4 Simulate an LMF connection by entering the sndtype 0xa178 command.
. . . continued on next page