Installation Instructions
Installation and ATP Order
PRELIMINARY
SCt300 BTS Hardware Installation, ATP and FRU Procedures
DEC 2000
1-32
Installation Order
The pieces of the MicroCell, PicoCell and Primary Surge Suppressor
units should be installed in the following order.
1. Unpack and inspect hardware.
2. Install mounting hardware and bracket(s).
3. Install back solar cover to mounting bracket (required for outdoor
installations and optional for indoor applications).
4. Install back fin cover to unit (required for indoor installations).
5. Install RGPS.
6. Prepare site cabling.
7. Attach installation handles to unit (optional).
8. Attach and secure unit to mounting bracket.
9. Attach and secure Primary Surge Suppressor to mounting bracket
(optional).
10. Remove installation handles (if used).
11. Remove Site I/O dust cover.
12. Attach Site I/O junction box to unit.
13. Attach all ground cabling to unit(s).
14. Attach all cables to unit(s).
15. Install short duration battery (if required).
16. Attach front solar cover (optional).
17. Attach front fin cover (optional).
ATP Order
The ATP for the MicroCell and PicoCell units is performed in the
following sequence:
1. BTS preparation.
2. Connecting the LMF to the BTS.
3. Connecting test equipment to the BTS and LMF.
4. Establishing an MMI communications session.
5. Setting customer operating channel.
6. Synchronization verification.
7. Install LMF program and binaries.
8. Start LMF and log on to BTS.
9. Update BTS–specific CDF file device load version.
10. Download and enable MAWI.
11. Test equipment setup (R3465 Calibration/GPIB address & clock
setup).
12. Test equipment selection.
13. Power meter calibration.
1