Initial Power Up – continued
08/15/2000
2-7
SC 4812ETL BTS Optimization/ATP
PRELIMINARY
Figure 2-4: ACLC Circuit Breaker Panel
LEDs
SC4812ETL0008–1
Figure 2-5: DC Power Distribution Assembly
SC4812ETL0009–1
Power Application Pre-test
Before applying any power to the BTS cabinet, follow the procedure in
Table 2-4 to verify there are no shorts in the DC power distribution
system.
The following procedure is required only on initial BTS
power–up or following maintenace when any major power
components (e.g., DC PDA, ACLC) were replaced or DC
power cables were disconnected.
NOTE