t ! " ! Release 2.15.x.x and CDMA LMF Build 2.15.x.
Notice While reasonable efforts have been made to assure the accuracy of this document, Motorola, Inc. assumes no liability resulting from any inaccuracies or omissions in this document, or from use of the information obtained herein. The information in this document has been carefully checked and is believed to be entirely reliable. However, no responsibility is assumed for inaccuracies or omissions. Motorola, Inc.
Table of Contents SC 4812ETL BTS Optimization/ATP Release 2.15.x.x and CDMA LMF Build 2.15.x.x List of Figures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . iv List of Tables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . vi Product Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . xi Foreword . . . . . . . . . . . . . . . . . . . . . . .
Table of Contents – continued Download the BTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-30 CSM System Time – GPS & LFR/HSO Verification . . . . . . . . . . . . . . . . . . . . . 3-37 Test Equipment Setup . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-47 Test Set Calibration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Table of Contents – continued Appendix A: Site Serial Number Check List . . . . . . . . . . . . . . . . . . . . . . . . . . . A-13 Appendix B: FRU Optimization/ATP Test Matrix Appendix B: FRU Optimization/ATP Test Matrix . . . . . . . . . . . . . . . . . . . . . . . B-1 Appendix C: BBX Gain Set Point vs. BTS Output Considerations Appendix C: BBX2 Gain Set Point vs. BTS Output Considerations . . . . . . . . .
List of Figures SC 4812ETL BTS Optimization/ATP Release 2.15.x.x and CDMA LMF Build 2.15.x.x iv Figure 1-1: Typical Logical BTS Configurations . . . . . . . . . . . . . . . . . . . . . . . . 1-15 Figure 1-2: SC4812ETL Cabinet . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-16 Figure 1-3: Internal Assemblies and FRUs (Cabinet doors not shown for clarity) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-17 Figure 1-4: SCCP Shelf . . . . . . . . . . . . . .
List of Figures – continued 08/15/2000 Figure 3-14: TX Calibration Test Setup (CyberTest and HP 8935) . . . . . . . . . . 3-51 Figure 3-15: TX Calibration Test Setup HP 8921A and Advantest . . . . . . . . . . 3-52 Figure 3-16: Optimization/ATP Test Setup Calibration (CyberTest, HP 8935 and Advantest) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-53 Figure 3-17: Optimization/ATP Test Setup HP 8921A . . . . . . . . . . . . . . . . . . .
List of Tables SC 4812ETL BTS Optimization/ATP Release 2.15.x.x and CDMA LMF Build 2.15.x.x vi Table 1-1: Non–Standard Terms and Abbreviations . . . . . . . . . . . . . . . . . . . . . . 1-13 Table 1-2: SCCP Shelf/Cage Card/Module Device ID Numbers (Top Shelf) . . 1-15 Table 1-3: SCCP Shelf/Cage Card/Module Device ID Numbers (Bottom Shelf) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-15 Table 1-4: BTS Sector Configuration . . . . . . . . . . .
List of Tables – continued 08/15/2000 Table 3-16: Enable CSMs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-35 Table 3-17: Enable MCCs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-36 Table 3-18: Test Equipment Setup (GPS & LFR/HSO Verification) . . . . . . . . . 3-39 Table 3-19: GPS Initialization/Verification . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-41 Table 3-20: LORAN–C Initialization/Verification .
List of Tables viii – continued Table 3-51: Multiple Rectifier Failure or Major Alarm . . . . . . . . . . . . . . . . . . . 3-88 Table 3-52: Single Rectifier Fail or Minor Alarm . . . . . . . . . . . . . . . . . . . . . . . 3-88 Table 3-53: Multiple Rectifier Failure or Major Alarm . . . . . . . . . . . . . . . . . . . 3-88 Table 3-54: Battery Over Temperature Alarm . . . . . . . . . . . . . . . . . . . . . . . . . . 3-89 Table 3-55: Rectifier Over Temperature Alarm . . . . . . . . . . . . . . .
List of Tables – continued 08/15/2000 Table 6-13: Troubleshooting Carrier Measurement Failure . . . . . . . . . . . . . . . . 6-10 Table 6-14: Troubleshooting Multi-FER Failure . . . . . . . . . . . . . . . . . . . . . . . . 6-11 Table 6-15: No GLI2 Control via LMF (all GLI2s) . . . . . . . . . . . . . . . . . . . . . . 6-16 Table 6-16: No GLI2 Control through Span Line Connection (Both GLI2s) . . 6-16 Table 6-17: MGLI2 Control Good – No Control over Co–located GLI2 . . . . .
List of Tables – continued Table F-1: HP8921A/600 Communications Test Set Rear Panel Connections Without Rubidium Reference . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . F-1 x Table F-2: HP8921A/600 Communications Test Set Rear Panel Connections With Rubidium Reference . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . F-3 Table F-3: System Connectivity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Product Information Model & Options Charts Refer to the SC 4812ET Lite Field Replaceable Units manual (68P TBS) for detailed model structure and option information This document covers only the steps required to verify the functionality of the Base Transceiver Subsystem (BTS) equipment prior to system level testing, and is intended to supplement site specific application instructions. It also should be used in conjunction with existing product manuals. Additional steps may be required.
Foreword Scope of manual This manual is intended for use by cellular telephone system craftspersons in the day-to-day operation of Motorola cellular system equipment and ancillary devices. It is assumed that the user of this information has a general understanding of telephony, as used in the operation of the Public Switched Telephone Network (PSTN), and is familiar with these concepts as they are applied in the cellular mobile/portable radiotelephone environment.
Foreword – continued The following special paragraphs are used in tables in the manual to point out information that must be read. NOTE Presents additional, helpful non-critical information that you can use. * IMPORTANT Presents information to help you avoid an undesirable situation or provide additional information to help you understand a topic or concept. ! CAUTION Presents information to identify a situation where equipment damage could occur and help you avoid damaging your equipment.
Foreword – continued Reporting manual errors In the event that you locate an error or identify a deficiency in your manual, please take time to write to us at the address above. Be sure to include your name and address, the complete manual title and part number (located on the manual spine, cover, or title page), the page number (found at the bottom of each page) where the error is located, and any comments you may have regarding what you have found.
General Safety Remember! . . . Safety depends on you!! The following general safety precautions must be observed during all phases of operation, service, and repair of the equipment described in this manual. Failure to comply with these precautions or with specific warnings elsewhere in this manual violates safety standards of design, manufacture, and intended use of the equipment. Motorola, Inc. assumes no liability for the customer’s failure to comply with these requirements.
General Safety – continued Use caution when exposing or handling the CRT Breakage of the Cathode–Ray Tube (CRT) causes a high-velocity scattering of glass fragments (implosion). To prevent CRT implosion, avoid rough handling or jarring of the equipment. The CRT should be handled only by qualified maintenance personnel, using approved safety mask and gloves.
Revision History Manual Number 68P09250A99–1 Manual Title SC 4812ETL BTS Optimization/ATP Release 2.15.x.x and CDMA LMF Build 2.15.x.x Version Information The following table lists the manual version , date of version, and remarks on the version.
Patent Notification Patent numbers This product is manufactured and/or operated under one or more of the following patents and other patents pending: 4128740 4193036 4237534 4268722 4282493 4301531 4302845 4312074 4350958 4354248 4367443 4369516 4369520 4369522 4375622 4485486 4491972 4517561 4519096 4549311 4550426 4564821 4573017 4581602 4590473 4591851 4616314 4636791 4644351 4646038 4649543 4654655 4654867 xviii 4661790 4667172 4672657 4694484 4696027 4704734 4709344 4710724 4726050 4729531 4737978
1 Chapter 1: Introduction Table of Contents 08/15/2000 Optimization Manual Scope and Layout . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Manual Scope and Layout . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Assumptions and Prerequisites . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Document Composition . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-1 1-1 1-1 1-2 Purpose of the Optimization . . . . . . . . . . . . . . .
1 Table of Contents – continued Notes SC 4812ETL BTS Optimization/ATP 08/15/2000 PRELIMINARY
Optimization Manual Scope and Layout 1 Manual Scope and Layout This document provides information pertaining to the optimization and audit tests of the Motorola SC4812ET Lite RF Base Transceiver Station (BTS) equipment frame and its associated internal and external interfaces.
1 Optimization Manual Scope and Layout – continued Document Composition This document covers the following major areas: S Introduction, consisting of preliminary background information (such as component and subassembly locations and frame layouts) to be considered by the Cellular Field Engineer CFE before performing optimization or tests.
Purpose of the Optimization 1 Why Optimize? Proper optimization and calibration ensures that: S Accurate downlink RF power levels are transmitted from the site. S Accurate uplink signal strength determinations are made by the site. What Is Optimization? Optimization compensates for the site-specific cabling and normal equipment variations.
1 When to Optimize New Installations After the initial site installation, the BTS must be prepared for operation. This preparation includes verifying hardware installation, initial power–up, downloading of operating code, verifying GPS operation and verifying transmit and receive paths. Next, the optimization is performed. Optimization includes performance verification and calibration of all transmit and receive RF paths, and download of accumulated calibration data.
Required Test Equipment and Software 1 Policy To ensure consistent, reliable, and repeatable optimization test results, test equipment and software meeting the following technical criteria should be used to optimize the BTS equipment. Test equipment can, of course, be substituted with other test equipment models if the equipment meets the same technical specifications.
1 Required Test Equipment and Software – continued Required Test Equipment and Software The following test equipment and software is required for the optimization procedure. You will also need common assorted tools such as screwdrivers and frame keys. Read the owner’s manual for all of the test equipment to understand its individual operation before using the tool in the optimization. NOTE Always refer to specific OEM test equipment documentation for detailed operating instructions.
Required Test Equipment and Software – continued 1 S Maintenance S Calibration S Optimization Ethernet LAN Transceiver (part of CGDSLMFCOMPAQNOV96) S PCMCIA Ethernet Adpater + Ethernet UTP Adapter 3COM Model – Etherlink III 3C589B used with S Transition Engineering Model E–CX–TBT–03 10BaseT/10Base2 Converter (or equivalent) NOTE Xircom Model PE3–10B2 or its equivalent can also be used to interface the CDMA LMF Ethernet connection to the RFM frame.
1 Required Test Equipment and Software – continued Communications system analyzer CDMA/analog The following communications system analyzers are supported by the LMF: S Motorola CyberTest S Advantest R3465 Analyzer with R3561L Signal Generator S Hewlett Packard Model HP 8921A/600 Analyzer including 83203B CDMA Interface, manual control system card, and 83236A/B PCS Interface for 1900 MHz BTSs.
Required Test Equipment and Software – continued 1 Timing reference cables S Two Huber & Suhner 16MCX/11BNC/K02252D or equivalent; right angle MCX–male to standard BNC–male RG316 cables; 10 ft.
1 Required Test Equipment and Software – continued Optional Equipment This section provides a list of additional equipment that might be required during maintenance and troubleshooting operations. NOTE Not all optional equipment specified in this section will be supported by the CDMA LMF in automated tests. Duplexer Filtronics Low IM Duplexer (Cm035–f2) or equivalent; used during Spectral Purity Receive band noise tests.
Required Test Equipment and Software – continued 1 troubleshooting. Do not substitute other models that do not feature special test modes. Two radios will be required for system and drive–around testing after optimization and BTS ATP are completed. RF circulator Circulator (FERROCOM 5809866C01) or equivalent; can substitute for a duplexer during Receive sensitivity FER testing in conjunction with Safco CDMA mobile. High stability 10 MHz rubidium standard Stanford Research Systems SR625 or equivalent.
1 Required Documents and Related Publications Required Documents The following documents are required to perform optimization of the cell site equipment: S Site Document (generated by Motorola Systems Engineering), which includes: – General site information – Floor plan – RF power levels – Frequency plan (includes Site PN and operating frequencies) – Channel allocation (paging, traffic, etc.
Terms and Abbreviations 1 Overview Standard terms and abbreviations used in this manual are defined in Cellular Glossary of Terms and Acronyms – 68P09213A95. Any non–standard terms or abbreviations included in this manual are listed in Table 1-1.
1 BTS Equipment Identification Equipment Overview The SC4812ETL BTS consists of a single, outdoor, weatherized cabinet containing RF and power components. The BTS is functionally similar to the two–cabinet SC4812ET, but provides more flexibility in site selection because of its smaller footprint and lighter weight. The BTS is powered by 220 Vac, rectified internally to +27 Vdc, and can support two carriers in a 3–sector configuration.
BTS Equipment Identification – continued 1 Table 1-2: SCCP Shelf/Cage Card/Module Device ID Numbers (Top Shelf) Frame # Card/Module ID Number (Left to Right) Power Power AMR GLI2 (PS–1) (PS–2) –1 –1 MCC2 BBX2 BBX2 –R MPC/ EMPC –1 1 – – 1 1 1 2 1 2 3 R1 – 101 – – 101 101 101 102 101 102 103 R101 – Table 1-3: SCCP Shelf/Cage Card/Module Device ID Numbers (Bottom Shelf) Frame # Card/Module ID Number (Left to Right) HSO/ CSM CSM CCD CCD LFR –1 –2 A B AMR GLI2– –2 2 1 – 1 2
1 Cabinet Identification Major Components Figure 1-2 illustrates the features of the BTS Cabinet, the single major component of the Motorola SC4812ETL.
Internal Assembly Location and Identification 1 Internal Assemblies and FRUs Figure 1-3 shows the location of the internal assemblies and Field Replaceable Units (FRU). A brief description of each item is found in the following paragraphs.
1 Internal Assembly Location and Identification – continued Duplexer/Directional Coupler (DRDC) The DRDC combines, in a single module, the functions of antenna duplexing, receive band pass filtering, and surge protection (see Figure 1-6). Filter/Combiner Shelf (Bandpass Filters or 2:1 Combiners) The Filter/Combiner Shelf holds the transmit band pass filters or 2:1 combiners, depending on system configuration.
Internal Assembly Location and Identification – continued 1 BBX2 BBX2 BBX2 BBX2 SWITCH 1 MPC BBX2 BBX2 MCC24 BBX2 GLI2 MCC24 MCC24 MCC24 AMR AMR GLI2 Power Supply 1 1 AMR GLI2 2 2 CIO MPC CCD CSM CSM HSO CCD Power Supply 19mm Filler Panel Figure 1-4: SCCP Shelf FILLER HSO/LFR FILLER HSO/LFR POWER 1 CSM 1 POWER 1 CSM 101 POWER 2 CSM 2 CCD 1 4 101 101 101 102 AMR GLI2 MCC CCD 102 102 103 104 POWER 2 CSM 102 2 MCC 3 4 2 3 BBX2 5 6 FRAME 1 SWITCH 1 MPC 2 101 102 103
1 Internal Assembly Location and Identification – continued Punch Block The Punch Block is the interface between the cabinet and the T1/E1 span lines, the Customer I/O, alarms, multi–cabinet timing (RGPS and RHSO), and Pilot Beacon control (optional). Span I/O Board The Span I/O Board provides the interface for the span lines from the CSU to the SCCP backplane (see Figure 1-3).
Internal Assembly Location and Identification – continued 1 AC Load Center (ACLC) The ACLC is the cabinet entry point for AC power. It incorporates AC power distribution and surge protection (See Figure 1-3).
1 BTS Sector Configurations Sector Configuration There are a number of ways to configure the BTS frame. Table 1-4 outlines the basic requirements. For more detailed information also see Table 1-5 and Figure 1-7. When carrier capacity is greater than two, a 2:1 cavity combiner must be used. For one or two carriers, bandpass filters or cavity combiners may be used, depending on sectorization and channel sequencing.
BTS Sector Configurations – continued 1 Table 1-5: Sector Configurations Configuation 1 2 3 4 5 08/15/2000 Description 3–Sector / 1 Carrier The configuration below maps RX and TX with bandpass filters or 2:1 combiners for a 3–sector/1–carrier frame.
1 BTS Sector Configurations – continued Figure 1-7: SC4812ETL LPA Configuration with Combiners/Filters Table 1-5 Configuration Numbers 1, 3, 4 Table 1-5 Configuration Numbers 2, 5 Bandpass Filters 2:1 Cavity Combiners 3–Sector 3–Sector CARRIER 1 SECTOR 1, 2, 3 CARRIER 2 SECTOR 1, 2, 3 SC4812ETL0011–1 1-24 SC 4812ETL BTS Optimization/ATP 08/15/2000 PRELIMINARY
Chapter 2: Preliminary Operations Table of Contents 08/15/2000 Preliminary Operations: Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Cell Site Types . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . CDF . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Table of Contents – continued Notes 2 SC 4812ETL BTS Optimization/ATP 08/15/2000 PRELIMINARY
Preliminary Operations: Overview Introduction This section first verifies proper frame equipage. This includes verifying module placement, jumper, and dual in–line package (DIP) switch settings against the site-specific documentation supplied for each BTS application. Next, pre-power up and initial power-up procedures are presented. Cellsite Types Sites are configured as 3–sectored with one or two carriers. Each type has unique characteristics and must be optimized accordingly.
Preliminary Operations: Overview – continued Setting Frame SCCP Shelf Configuration Switch If the frame is a Starter BTS, the backplane switch settings behind the right–hand SCCP shelf fan module should be set to the ON position (see Figure 2-1). 2 The switch setting must be verified and set before power is applied to the BTS equipment.
Initial Power Up Introduction The following information is used to check for any electrical short circuits and to verify the operation and tolerances of the cell site and BTS power supply units before applying power for the first time. It contains instructional information on the proper initial power up procedures for the SC4812ETL. Please pay attention to all cautions and warning statements in order to prevent accidental injury to personnel. Required Tools The following tools are used in the procedures.
Initial Power Up – continued CAUTION Failure to properly connect the external AC power cable will damage the surge protection module inside the AC load center. 2 Power–Up Sequence The first task in the power–up sequence is to apply external AC power to the cabinet. Once power is applied, a series of AC Voltage measurements is required.
Initial Power Up – continued Figure 2-2: AC Load Center External Power Connections Remove torx screw to remove ACLC rear cover.
Initial Power Up – continued Figure 2-3: Cabinet Power Subassemblies External Blower Assembly 2 LPAs Battery Shelf Circuit Breakers AC Rectifiers Meter Alarm Panel With TCU SCCP Fans ETIB SCCP Shelf RFDS DC PDA ACLC GFCI Utility Outlet Backup Batteries (Heaters underneath batteries) SC4812ETL0002–2 2-6 SC 4812ETL BTS Optimization/ATP 08/15/2000 PRELIMINARY
Initial Power Up – continued Figure 2-4: ACLC Circuit Breaker Panel LEDs 2 SC4812ETL0008–1 Figure 2-5: DC Power Distribution Assembly SC4812ETL0009–1 Power Application Pre-test Before applying any power to the BTS cabinet, follow the procedure in Table 2-4 to verify there are no shorts in the DC power distribution system. NOTE The following procedure is required only on initial BTS power–up or following maintenace when any major power components (e.g.
Initial Power Up – continued Table 2-4: Pre–power DC Power Distribution System Test 2 Step Action 1 Physically verify that circuit breakers on the ACLC (Figure 2-4) and DC PDA (figure Figure 2-5), and all battery shelf circuit breakers (Figure 2-3), are OFF. 2 Visually ensure that all AC rectifier modules (Figure 2-3) are not powered (DC, Power, and bar graph LEDs are not lighted). 3 Inside the battery compartment, measure the voltage between the + (red) and – (black) battery bus bars.
Initial Power Up – continued Table 2-4: Pre–power DC Power Distribution System Test Step Action 13 Seat the Pilot Beacon, Heat Exchanger, ETIB, and Options circuit breakers to ON one at a time. Repeat step 5 after pushing in each circuit breaker. 14 Set all DC PDA circuit breakers to OFF (pulled out). 2 Applying AC Power Once AC voltage measurements are complete, apply AC power to the Power Cabinet. Table 2-5 provides the procedure for applying AC power.
Initial Power Up – continued Figure 2-7: Temperature Compensation Panel TEMPERATURE COMPENSATION PANEL 2 1/2 A 250V OFF ON ON SENSOR SENSE COM 1 2 + – 25_ c V ADJ FRONT VIEW Power Cabinet Power Up Tests Table 2-6 lists the step–by–step instructions for Power Up Tests. Table 2-6: Cabinet DC Power–Up Tests Step Action 1 Ensure ALL DC PDA circuit breakers are OFF (pulled out). 2 Be sure the procedures in Table 2-4 (if required) and (Table 2-5) have been performed.
Initial Power Up – continued Battery Charge Test (Connected Batteries) Table 2-7 lists the step–by–step instructions for testing the batteries. 2 Table 2-7: Battery Charge Test (Connected Batteries) Step Action 1 Close the battery shelf circuit breakers (Figure 2-3) for connected batteries ONLY.
Initial Power Up – continued Battery Discharge Test Perform the test procedure in Table 2-8 only when the battery current is less than 5 A per string. Refer to Table 2-7 on the procedures for checking current levels. 2 Table 2-8: Battery Discharge Test Step Action 1 Turn the battery test switch on the Meter Alarm Panel, ON (see Figure 2-6). The rectifier output voltage and current should decrease by approximately 10% as the batteries assume the load. Alarms for the Meter Alarm Panel may occur.
Initial Power Up – continued Figure 2-8: Heat Exchanger Blower Assembly and Circuit Breakers Heat Exchanger Assembly Top (Internal) Blower Blower Power Cord 2 Mounting Bracket Bottom (Ambient) Blower Fan Module Mounting Bracket Core Fan Module T–30 Screw T–30 Screw Blower Power Cord DC PDA OUT=OFF IN=ON Heat Exchanger Blower Assembly Circuit Breaker Side View 08/15/2000 SC 4812ETL BTS Optimization/ATP PRELIMINARY 2-13
Initial Power Up – continued Notes 2 2-14 SC 4812ETL BTS Optimization/ATP 08/15/2000 PRELIMINARY
Chapter 3: Optimization/Calibration Table of Contents 3 Optimization/Calibration – Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Optimization Process . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Cell Site Types . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Cell Site Data File (CDF) . . . . . . . . . . .
Table of Contents 3 – continued Online Help . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-26 Pinging the Processors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Pinging the BTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-27 3-27 Download the BTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Overview . . . . . . . . . . . .
Table of Contents 08/15/2000 – continued Transmit (TX) Path Audit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . TX Audit Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . All Cal/Audit Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Create CAL File . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-71 3-72 3-73 3-74 RFDS Setup and Calibration . . . . . . . . . .
Table of Contents – continued Notes 3 SC 4812ETL BTS Optimization/ATP 08/15/2000 PRELIMINARY
Optimization/Calibration – Introduction Introduction This chapter provides procedures for downloading system operating software, set up of the supported test equipment, CSM reference verification/optimization, and transmit/receive path verification. IMPORTANT * Before using the LMF, use an editor to view the ”CAVEATS” section in the ”readme.txt” file in the c:\wlmf folder for any applicable information.
Optimization/Calibration – Introduction – continued calibration, BLO download, TX audit, all TX tests, and all RX tests for all selected devices. S If the TX calibration fails, repeat the full optimization for any failed paths. S If the TX calibration fails again, correct the problem that caused the failure and repeat the full optimization for the failed path.
Pre–Optimization: Introduction – continued BTS System Software Download BTS system software must be successfully downloaded to the BTS processor boards before optimization can be performed. BTS operating code is loaded from the LMF computer terminal. IMPORTANT * Before using the LMF for optimization/ATP, the correct bts–#.cdf and cbsc–#.cdf files for the BTS must be obtained from the CBSC and put in a bts–# folder in the LMF. Failure to use the correct CDF files can cause wrong results.
Span Lines – Interface and Isolation Isolate BTS from T1/E1 Spans IMPORTANT * 3 At active sites, the OMC/CBSC must disable the BTS and place it out of service (OOS). DO NOT remove the span surge protectors until the OMC/CBSC has disabled the BTS. Each frame is equipped with one 50 pair punch block for spans, customer alarms, remote GPS, and power cabinet alarms. See Figure 3-2 and refer to Table 3-1 for the physical location and pin call–out information.
Span Lines – Interface and Isolation – continued Setting the Control Port Whichever control port is chosen, it must first be set up so the control port switches match the communication parameters being used by the control device. If using the rear–panel DTE control port, set the shelf–address switch SA5 to “up” (leave the switch down for the rear–panel DCE control port). For more information, refer to the Kentrox Installation Guide, manual number 65–77538001 which is provided with each CSU.
Span Lines – Interface and Isolation – continued Alarm and Span Line Cable Pin/Signal Information See Figure 3-2 and refer to Table 3-1 for the physical location and pin call–out information for the 50–pin punch block.
Span Lines – Interface and Isolation – continued Table 3-1: Pin–Out for 50 Pin Punch Block Site Component POWER CABINET LFR / HSO PILOT BEACON Signal Name Power Cab Control – NC Power Cab Control – NO Power Cab Control – Com Reserved Rectifier Fail AC Fail Power Cab Exchanger Fail Power Cab Door Alarm Power Cab Major Alarm Battery Over Temp Power Cab Minor Alarm Reticifier Over Temp Power Cab Alarm Rtn LFR_HSO_GND EXT_1PPS_POS EXT_1PPS_NEG CAL_+ CAB_– LORAN_+ LORAN_– Pilot Beacon Alarm – Minor Pilot Be
Span Lines – Interface and Isolation – continued Table 3-1: Pin–Out for 50 Pin Punch Block Site Component 3 CUSTOMER OUTPUTS / INPUTS SPAN Signal Name Customer Outputs 1 – NO Customer Outputs 1 – COM Customer Outputs 1 – NC Customer Outputs 2 – NO Customer Outputs 2 – COM Customer Outputs 2 – NC Customer Outputs 3 – NO Customer Outputs 3 – COM Customer Outputs 3 – NC Customer Outputs 4 – NO Customer Outputs 4–COM Customer Outputs 4 – NC Customer Inputs 1 Cust_Rtn_A_1 Customer Inputs 2 Cust_Rtn_A_2 Cust
Span Lines – Interface and Isolation – continued Table 3-1: Pin–Out for 50 Pin Punch Block Site Component RGPS Phone Line Miscellaneo s Miscellaneous Signal Name GPS_POWER_1+ GPS_POWER_1– GPS_POWER_2+ GPS_POWER_2– GPS_RX+ GPS_RX– GPS_TX+ GPS_TX– Signal Ground (TDR+) Master Frame (TDR–) GPS_lpps+ GPS_lpps– Telco_Modem_T Telco_Modem_R Chasis Ground Reserved Reserved Reserved Pin 42T 42R 43T 43R 44T 44R 45T 45R 46T 46R 47T 47R 48T 48R 49T 49R 50T 50R Color Blue Bk/Blue Yellow Bk/Yellow White White Green
Preparing the LMF Overview Before optimization can be performed, the CDMA LMF must be installed and configured on a computer platform meeting Motorola–specified requirements (see Recommended Test Equipment and Software in Chapter 1). IMPORTANT * 3 For the CDMA LMF graphics to display properly, the computer platform must be configured to display more than 256 colors. See the operating system software instructions for verifying and configuring the display settings.
Preparing the LMF – continued Table 3-3: CD ROM Installation n Step Action 3 Select Run. 4 Enter d:\autorun in the Open box and click OK. NOTE (If applicable, replace the letter d with the correct CD ROM drive letter.) 5 3 Follow the directions displayed in the Setup screen. Copy CBSC CDF Files to the LMF Computer Before logging on to a BTS with the CDMA LMF computer to execute optimization/ATP procedures, the correct bts-#.cdf and cbsc-#.
Preparing the LMF – continued Table 3-4: Copying CBSC CDF Files to the LMF Computer Step 4 Action Type mount and press the Enter key. NOTE S Look for the “floppy/no_name” message on the last line displayed. S If the eject command was previously entered, floppy/no_name will be appended with a number. Use the explicit floppy/no_name reference displayed when performing step 7. 3 5 Change to the directory, where the files to be copied reside, by typing cd (e.g.
Preparing the LMF – continued Creating a Named HyperTerminal Connection for MMI Communication Confirming or changing the configuration data of certain BTS Field Replaceable Units (FRU) requires establishing an MMI communication session between the CDMA LMF computer and the FRU. Using features of the Windows operating system, the connection properties for an MMI session can be saved on the CDMA LMF computer as a named Windows HyperTerminal connection.
Preparing the LMF – continued Table 3-5: Create HyperTerminal Connection Step 5 Action In the Port Settings tab of the COM# Properties window displayed, configure the RS–232 port settings as follows: S S S S S 3 Bits per second: 9600 Data bits: 8 Parity: None Stop bits: 1 Flow control: None 6 Click OK. 7 Save the defined connection by selecting: File > Save 8 Close the HyperTerminal window by selecting: File > Exit 9 Click the Yes button to disconnect when prompted.
Preparing the LMF – continued Folder Structure Overview The CDMA LMF uses a wlmf folder that contains all of the essential data for installing and maintaining the BTS. The following list outlines the folder structure for CDMA LMF. Except for the bts-nnn folders, these folders are created as part of the CDMA LMF installation.
Preparing the LMF – continued Figure 3-4: BTS Folder Name Syntax Example bts–259 BTS Number 3 bts–nnn.cal File The CAL (Calibration) file contains the bay level offset data (BLO) that is used for BLO downloads to the BBX devices. The CAL file is automatically created and updated by the CDMA LMF when TX calibration is performed. Figure 3-5 details the file name syntax for the CAL file. Figure 3-5: CAL File Name Syntax Example bts–259.cal BTS Number bts–nnn.
Preparing the LMF – continued cbsc File The cbsc–#.cdf (Centralized Base Station Controller) file contains data for the BTS. If one is not obtained from the CBSC, a copy of the default cbsc–1.cdf file located in the cdma folder can be used. IMPORTANT * Using the generic cbsc–1.cdf file will not provide a valid optimization unless the generic file is edited to replace default parameters with local operational parameters (e.g.
Preparing the LMF – continued Figure 3-7: Code Load File Name Syntax Example bbx_ram.bin.0600 Device Type Hardware bin number If this number matches the bin number of the device, the code file will automatically be used for the download* 3 * The device bin number can be determined by using the Status function after logging into a BTS. If the device does not have a bin number, one of the following default numbers must be used.
Preparing the LMF – continued Figure 3-8: DDS File Name Syntax Example csm.dds.0800 Device Type Device Bin Type Number If this number matches the bin number of the device, the DDS file will automatically be used for the download* 3 * The device bin number can be determined by using the Status function after logging into a BTS. If the device does not have a bin number, one of the following default numbers must be used.
LMF to BTS Connection LMF to BTS Connection The CDMA LMF computer is connected to the LAN A or B connector located behind the frame lower air intake grill. Figure 3-9 below shows the general location of these connectors. Table 3-6: Connect the LMF to the BTS 3 Step Action 1 To gain access to the LAN connectors, open the LAN cable and utility shelf access panel, then pull apart the hook–and–loop tape covering the BNC “T” connector. If desired, slide out the utility shelf for the LMF computer.
Using CDMA LMF Basic CDMA LMF Operation The CDMA LMF allows the user to work in the two following operating environments which are accessed using the specified desktop icons: S Graphical User Interface (GUI) using the WinLMF icon S Command Line Interface (CLI) using the WinLMF CLI icon The GUI is the primary optimization and acceptance testing operating environment.
Using CDMA LMF – continued to the BTS (see Table 3-6). Follow the procedures in Table 3-7 to log into a BTS. Prerequisites Before attempting to login to a BTS, ensure the following have been completed: S The CDMA LMF is correctly installed and prepared. S A bts-nnn folder with the correct CDF and CBSC files exists. S The CDMA LMF computer was connected to the BTS before starting 3 the Windows operating system and the CDMA LMF software.
Using CDMA LMF – continued Table 3-7: BTS GUI Login Procedure n Step 10 Action Click on Login. (A BTS tab with the BTS is displayed.) NOTE S If you attempt to log into a BTS that is already logged on, all devices will be gray. S There may be instances where the BTS initiates a log out due to a system error (i.e., a device failure). 3 S If the MGLI is OOS–ROM (blue), it must be downloaded with RAM code before other devices can be seen.
Using CDMA LMF – continued BTS Login from the CLI Environment Follow the procedures in Table 3-8 to log into a BTS when using the CLI environment. IMPORTANT * 3 If the CLI and GUI environments are to be used at the same time, the GUI must be started first and BTS login must be performed from the GUI. Refer to Table 3-7 to start the GUI environment and log into a BTS.
Using CDMA LMF – continued IMPORTANT * The GUI and CLI environments use the same connection to a BTS. If a BTS is logged into in both the GUI and CLI environments at the same time, logging out of the BTS in either environment will log out of it for both. When the logout is performed in the CLI window, there is no GUI indication that logout has occurred. 3 Logging Out of a BTS from the GUI Environment Follow the procedure in Table 3-9 to logout of a BTS when using the GUI environment.
Using CDMA LMF – continued Logging Out of a BTS from the CLI Environment Follow the procedure in Table 3-10 to logout of a BTS when using the CLI environment. Table 3-10: BTS CLI Logout Procedure n Step Action * IMPORTANT If the BTS is also logged into from a GUI running at the same time and further work must be done with it in the GUI, proceed to step 2. 3 1 Logout of a BTS by entering the following command: logout bts– A response similar to the following will be displayed: LMF> 13:24:51.
Using CDMA LMF – continued Table 3-11: Establishing MMI Communication Step Action NOTE If a Windows desktop shortcut was not created for the MMI connection, access the connection from the Windows Start menu by selecting: Programs > Accessories > Hyperterminal > HyperTerminal >
Pinging the Processors Pinging the BTS For proper operation, the integrity of the Ethernet LAN A and B links must be be verified. NO TAG represents a typical BTS Ethernet configuration. The drawing depicts one (of two identical) links, A and B. Ping is a program that sends request packets to the LAN network modules to get a response from the specified “target” module. 3 Follow the steps in Table 3-12 to ping each processor (on both LAN A and LAN B) and verify LAN redundancy is working properly.
Map Title Goes Here – continued IMPORTANT * The Ethernet LAN A and B cables must be installed on each frame/enclosure before performing this test. All other processor board LAN connections are made via the backplanes. Table 3-12: Pinging the Processors Step 3 Action 1 From the Windows desktop, click the Start button and select Run. 2 In the Open box, type ping and the GLI2 IP address (for example, ping 128.0.0.2). NOTE 128.0.0.2 is the default IP address for the GLI2 in field BTS units.
Download the BTS Overview Before a BTS can operate, each equipped device must contain device initialization (ROM) code. ROM code is loaded in all devices during manufacture or factory repair. Device application (RAM) code and data must be downloaded to each equipped device by the user before the BTS can be made fully functional for the site where it is installed. ROM Code 3 Downloading ROM code to BTS devices from the CDMA LMF is NOT routine maintenance or a normal part of the optimization process.
Download the BTS – continued The devices to be loaded with RAM code and data are: S Master Group Line Interface (MGLI2) S Redundant GLI (GLI2) S Clock Syncronization Module (CSM) (Only if new revision code must be loaded) S Multi Channel CDMA (MCC24) card S Broadband Transceiver (BBX2) S RFDS Test Subscriber Interface Card (TSIC), if equipped 3 IMPORTANT * The MGLI must be successfully downloaded with RAM code and data, and in INS (green) status before downloading any other device.
Download the BTS – continued Download RAM Code and Data to MGLI and GLI Follow the steps outlined in Table 3-13 to download the RAM code and data to the MGLI and other installed GLI devices. CAUTION Release 2.9.x RAM code must NOT be downloaded to a device loaded with Release 2.8.x ROM code, and Release 2.8.x RAM code must NOT be downloaded to a device loaded with Release 2.9.x ROM code.
Download the BTS – continued Table 3-13: Download and Enable MGLI and GLI Devices Step 5 6 Action Once the MGLI is enabled, load and enable additional installed GLIs by clicking on the devices and repeating step 4. Click OK to close the status window for the additional GLI devices. 3 Download RAM Code and Data to Non–GLI Devices Downloads to non–GLI devices can be performed individually for each device or all installed devices can be downloaded with one action.
Download the BTS – continued Select CSM Clock Source A CSM can have three different clock sources. The Select CSM Source function can be used to select the clock source for each of the three inputs. This function is only used if the clock source for a CSM needs to be changed. The Clock Source function provides the following clock source options.
Download the BTS – continued IMPORTANT * For RF–GPS, verify the CSM configured with the GPS receiver “daughter board” is installed in the frame’s CSM 1 slot before continuing. Follow the steps outlined in Table 3-16 to enable the CSMs installed in the SCCP shelves. 3 Table 3-16: Enable CSMs Step 1 Action Click on the target CSM. From the Device pull down, select Enable. NOTE If equipped with two CSMs, enable CSM–2 first A status report is displayed confirming change in the device(s) status.
Download the BTS – continued but a timing adjustment that compensates for the processing delay in the BTS (approximately 3 mS). Follow the steps outlined in Table 3-17 to enable the MCCs installed in the SCCP shelves. IMPORTANT * 3 The MGLI and CSM must be downloaded and enabled, prior to downloading and enabling the MCC. Table 3-17: Enable MCCs Step Action 1 Click on the target MCC(s) or from the Select pull down menu choose All MCCs.
CSM System Time – GPS & LFR/HSO Verification Clock Synchronization Manager (CSM) System Time The primary function of the Clock Synchronization Manager (CSM) boards (slots 1 and 2) is to maintain CDMA system time. The CSM in slot 1 is the primary timing source while slot 2 provides redundancy. The CSM2 card (CSM second generation) is required when using the remote GPS receiver (R–GPS). R–GPS uses a GPS receiver in the antenna head that has a digital output to the CSM2 card.
CSM System Time – GPS & LFR/HSO Verification – continued The HSO is a high stability 10 MHz oscillator with the necessary interface to the CSMs. The HSO is typically installed in those geographical areas not covered by the LORAN–C system. Since the HSO is a free–standing oscillator, system time can only be maintained for 24 hours after 24 hours of GPS lock. Upgrades and Expansions: LFR2/HSO2/HSOX LFR2/HSO2 (second generation cards) both export a timing signal to the expansion or logical BTS frames.
CSM System Time – GPS & LFR/HSO Verification – continued CSM Frequency Verification The objective of this procedure is the initial verification of the Clock Synchronization Module (CSM) boards before performing the rf path verification tests. Parts of this procedure will be repeated for final verification after the overall optimization has been completed. Test Equipment Setup (GPS & LFR/HSO Verification) 3 Follow the steps outlined in Table 3-18 to set up test equipment.
CSM System Time – GPS & LFR/HSO Verification – continued Figure 3-12: CSM MMI Terminal Connection REFERENCE OSCILLATOR CSM board shown removed from frame MMI SERIAL PORT 3 EVEN SECOND TICK TEST POINT REFERENCE GPS RECEIVER ANTENNA INPUT ANTENNA COAX CABLE GPS RECEIVER 19.6 MHZ TEST POINT REFERENCE (NOTE 1) NULL MODEM BOARD (TRN9666A) 9–PIN TO 9–PIN RS–232 CABLE FW00372 LMF NOTEBOOK DB9–TO–DB25 ADAPTER COM1 NOTES: 1.
CSM System Time – GPS & LFR/HSO Verification – continued Table 3-19: GPS Initialization/Verification Step Action 1 To verify that Clock alarms (0000), Dpll is locked and has a reference source, and GPS self test passed messages are displayed within the report, issue the following MMI command bstatus – Observe the following typical response: 3 CSM Status INS:ACTIVE Slot A Clock MASTER. BDC_MAP:000, This CSM’s BDC Map:0000 Clock Alarms (0000): DPLL is locked and has a reference source.
CSM System Time – GPS & LFR/HSO Verification – continued Table 3-19: GPS Initialization/Verification Step Action 3 HSO information (underlined text above, verified from left to right) is usually the #1 reference source. If this is not the case, have the OMCR determine the correct BTS timing source has been identified in the database by entering the display bts csmgen command and correct as required using the edit csm csmgen refsrc command.
CSM System Time – GPS & LFR/HSO Verification – continued Table 3-19: GPS Initialization/Verification Step 5 Action Enter the following command at the CSM> prompt to verify that the GPS receiver is in tracking mode.
CSM System Time – GPS & LFR/HSO Verification – continued Table 3-19: GPS Initialization/Verification Step 7 Action If steps 1 through 6 pass, the GPS is good. * IMPORTANT If any of the above mentioned areas fail, verify that: – If Initial position accuracy is “estimated” (typical), at least 4 satellites must be tracked and visible (1 satellite must be tracked and visible if actual lat, log, and height data for this site has been entered into CDF file).
CSM System Time – GPS & LFR/HSO Verification – continued LORAN–C Initialization/Verification Table 3-20: LORAN–C Initialization/Verification Step Action 1 At the CSM> prompt, enter lstatus to verify that the LFR is in tracking mode.
CSM System Time – GPS & LFR/HSO Verification – continued Table 3-20: LORAN–C Initialization/Verification Step Action Note 2 Verify the following LFR information (highlighted above in boldface type): – Locate the “dot” that indicates the current phase locked station assignment (assigned by MM). – Verify that the station call letters are as specified in site documentation as well as M X Y Z assignment. – Verify the S/N ratio of the phase locked station is greater than 8.
Test Equipment Setup Connecting Test Equipment to the BTS All test equipment is controlled by the LMF via IEEE–488/GPIB bus. The LMF requires each piece of test equipment to have a factory set GPIB address. If there is a communications problem between the LMF and any piece of test equipment, verify that the GPIB addresses have been set correctly (normally 13 for a power meter and 18 for a CDMA analyzer).
Test Equipment Set–up – continued Test Equipment Setup Chart Table 3-21 depicts the current test equipment available meeting Motorola standards. To identify the connection ports, locate the test equipment presently being used in the TEST SETS columns, and read down the column. Where a ball appears in the column, connect one end of the test cable to that port. Follow the horizontal line to locate the end connection(s), reading up the column to identify the appropriate equipment/BTS port.
Test Equipment Set–up – continued Equipment Warm-up IMPORTANT * Warm-up BTS equipment for a minimum of 60 minutes prior to performing the BTS optimization procedure. This assures BTS site stability and contributes to optimization accuracy. (Time spent running initial power-up, hardware/firmware audit, and BTS download counts as warm-up time.) WARNING Before installing any test equipment directly to any BTS TX OUT connector, verify there are NO CDMA BBX channels keyed.
Test Equipment Set–up – continued Figure 3-13: Cable Calibration Test Setup SUPPORTED TEST SETS CALIBRATION SET UP Motorola CyberTest A. SHORT CABLE CAL ÏÏÏ ÏÏÏÌ 3 SHORT CABLE ANT IN TEST SET RF GEN OUT Note: The Directional Coupler is not used with the Cybertest Test Set. The TX cable is connected directly to the Cybertest Test Set. B. RX TEST SETUP A 10dB attenuator must be used with the short test cable for cable calibration with the CyberTest Test Set.
Test Equipment Set–up – continued Setup for TX Calibration Figure 3-14 and Figure 3-15 show the test set connections for TX calibration. Figure 3-14: TX Calibration Test Setup (CyberTest and HP 8935) TEST SETS TRANSMIT (TX) SET UP Motorola CyberTest POWER SENSOR 100–WATT (MIN) NON–RADIATING RF LOAD ÏÏÏ ÏÏÏÌ FRONT PANEL 3 POWER METER (OPTIONAL)* OUT DIRECTIONAL COUPLER (30 DB) RF IN/OUT 2O DB PAD FOR 1.9 GHZ NOTE: THE DIRECTIONAL COUPLER IS NOT USED WITH THE CYBERTEST TEST SET.
Test Equipment Set–up – continued Figure 3-15: TX Calibration Test Setup HP 8921A and Advantest TEST SETS TRANSMIT (TX) SET UP NOTE: THE HP8921A AND ADVANTEST CANNOT BE USED FOR TX CALIBRATION. A POWER METER MUST BE USED. 100–WATT (MIN) NON–RADIATING RF LOAD POWER SENSOR POWER METER 3 DIRECTIONAL COUPLER (30 DB) TX TEST CABLE 2O DB PAD FOR 1.
Test Equipment Set–up – continued Setup for Optimization/ATP Figure 3-16 and Figure 3-17 show the test set connections for optimization/ATP tests. Figure 3-16: Optimization/ATP Test Setup Calibration (CyberTest, HP 8935 and Advantest) TEST SETS Optimization/ATP SET UP Motorola CyberTest SYNC MONITOR EVEN SEC TICK PULSE REFERENCE FROM CSM BOARD FREQ MONITOR 19.
Test Equipment Set–up – continued Figure 3-17: Optimization/ATP Test Setup HP 8921A TEST SETS Optimization/ATP SET UP Hewlett–Packard Model HP 8921A W/PCS Interface (for 1700 and 1900 MHz) SYNC MONITOR EVEN SEC TICK PULSE REFERENCE FROM CSM BOARD FREQ MONITOR 19.6608 MHZ CLOCK REFERENCE FROM CSM BOARD NOTE: IF BTS RX/TX SIGNALS ARE DUPLEXED (4800E): BOTH THE TX AND RX TEST CABLES CONNECT TO THE DUPLEXED ANTENNA GROUP.
Test Set Calibration Background Proper test equipment setup ensures that the test equipment and associated test cables do not introduce measurement errors, and that measurements are correct. NOTE If the test set being used to interface with the BTS has been calibrated and maintained as a set, this procedure does not need to be performed. (Test Set includes LMF terminal, communications test set, additional test equipment, associated test cables, and adapters.
Test Set Calibration – continued Selecting Test Equipment Use LMF Options from the Options menu list to select test equipment automatically (using the autodetect feature) or manually. Prerequisites A Serial Connection and a Network Connection tab are provided for test equipment selection. The Serial Connection tab is used when the test equipment items are connected directly to the CDMA LMF computer via a GPIB box (normal setup).
Test Set Calibration – continued Automatically Selecting Test Equipment in a Serial Connection Tab When using the auto-detection feature to select test equipment, the CDMA LMF examines which test equipment items are actually communicating with CDMA LMF. Follow the procedure in Table 3-23 to use the auto-detect feature. Table 3-23: Selecting Test Equipment Using Auto-Detect Step 3 Action 1 From the Options menu, select LMF Options. The LMF Options window appears.
Test Set Calibration – continued Calibrating Test Equipment The calibrate test equipment function zeros the power measurement level of the test equipment item that is to be used for TX calibration and audit. If both a power meter and an analyzer are connected, only the power meter is zeroed. Calibrate Test Equipment from the Util menu list is used to calibrate test equipment item before being used for testing. The test equipment must be selected before beginning calibration.
Test Set Calibration – continued Calibrating Cables with a CDMA Analyzer The Cable Calibration menu item from the Util menu list is used to calibrate both TX and RX test cables for use with CDMA LMF. NOTE LMF cable calibration cannot be accomplished with an HP8921A analyzer for 1.9 MHz. A different analyzer type or the signal generator and spectrum analyzer method must be used (refer to Table 3-26 and Table 3-27).
Test Set Calibration – continued Calibrating TX Cables Using a Signal Generator and Spectrum Analyzer Follow the procedure in Table 3-26 to calibrate the TX cables using the signal generator and spectrum analyzer. Refer to Figure 3-18 for a diagram of the signal generator and spectrum analyzer. Table 3-26: Calibrating TX Cables Using Signal Generator and Spectrum Analyzer 3 Step Action 1 Connect a short test cable between the spectrum analyzer and the signal generator.
Test Set Calibration – continued Calibrating RX Cables Using a Signal Generator and Spectrum Analyzer Follow the procedure in Table 3-27 to calibrate the RX cables using the signal generator and spectrum analyzer. Refer to Figure 3-19, if required. Table 3-27: Calibrating RX Cables Using a Signal Generator and Spectrum Analyzer Step Action 1 Connect a short test cable to the spectrum analyzer and connect the other end to the Signal Generator.
Test Set Calibration – continued Setting Cable Loss Values Cable loss values for the TX and RX test cable configurations are normally set by accomplishing cable calibration with use of the applicable test equipment. The resulting values are stored in the cable loss files. The cable loss values can also be set/changed manually. Prerequisites S Logged into the BTS 3 Table 3-28: Setting Cable Loss Values Step Action 1 Click on the Util menu. 2 Select Edit >Cable Loss > TX or RX.
Test Set Calibration – continued Setting TX Coupler Loss Value If an in–service TX coupler is installed the coupler loss (e.g., 30 dB) must be manually entered so it will be included in the LMF TX calibration and audit calculations. Prerequisites S Logged into the BTS Table 3-29: Setting TX Coupler Loss Values Step Action 1 Click on the Util menu. 2 Select Edit >TX Coupler Loss. A data entry pop–up window will appear.
Bay Level Offset Calibration Introduction Calibration compensates for normal equipment variations within the BTS and assures maximum measurement accuracy. RF Path Bay Level Offset Calibration Calibration identifies the accumulated gain in every transmit path (BBX2 slot) at the BTS site and stores that value in the CAL file. The BLOs are subsequently downloaded to each BBX2. 3 Each receive path starts at a BTS RX antenna port and terminates at a backplane BBX2 slot.
Bay Level Offset Calibration – continued TX Path Calibration The TX Path Calibration assures correct site installation, cabling, and the first order functionality of all installed equipment. The proper function of each RF path is verified during calibration. The external test equipment is used to validate/calibrate the TX paths of the BTS. WARNING Before installing any test equipment directly to any TX OUT connector you must first verify that there are no CDMA channels keyed.
Bay Level Offset Calibration – continued BLO Calibration Data File During the calibration process, the LMF creates a calibration (BLO) data file. After calibration has been completed, this offset data must be downloaded to the BBX2s using the Download BLO function. An explanation of the file is shown below. NOTE Due to the size of the file, Motorola recommends that you print out a hard copy of a bts.cal file and refer to it for the following descriptions.
Bay Level Offset Calibration – continued – The second breakdown of the array is per sector. Three sectors are allowed. Table 3-31: BTS.
Bay Level Offset Calibration – continued file. TxCal data is sent first, C[1] – C[60]. BBX2 slot 1’s 10 calibration points are sent (C[1] – C[20]), followed by BBX2 slot 2’s 10 calibration points (C[21] – C[40]), etc. The RxCal data is sent next, followed by the RxDCal data. S Temperature compensation data is also stored in the cal file for each slot. 3 Test Equipment Setup: RF Path Calibration Follow the steps outlined in Table 3-32 to set up test equipment.
Bay Level Offset Calibration – continued –2.0 dBm) and RFDS directional coupler/cable (approximately –0.6 dBm) would equate to 41.4 dB BLO. The LMF Tests menu list items, TX Calibration and All Cal/Audit, perform the TX BLO Calibration test for a XCVR(s). The All Cal/Audit menu item performs TX calibration, downloads BLO, and performs TX audit if the TX calibration passes. All measurements are made through the appropriate TX output connector using the calibrated TX cable setup.
Bay Level Offset Calibration – continued Table 3-33: BTS TX Path Calibration Step Action 1 Select the BBX2(s) to be calibrated. 2 From the Tests menu, select TX Calibration or All Cal/Audit. 3 4 Select the appropriate carrier(s) displayed in the Channels/Carrier pick list. Press and hold the or key to select multiple items. Type the appropriate channel number in the Carrier n Channels box. 5 Click on OK. 6 Follow the cable connection directions as they are displayed.
Bay Level Offset Calibration – continued Table 3-34: Download BLO Step Action 1 Select the BBX2(s) to be downloaded. 2 From the Device menu, select Download BLO. A status report window displays the result of the download. NOTE 3 Selected device(s) do not change color when BLO is downloaded. Click OK to close the status report window.
Bay Level Offset Calibration – continued Calibration Audit Introduction The BLO calibration audit procedure confirms the successful generation and storage of the BLO calibrations. The calibration audit procedure measures the path gain or loss of every BBX2 transmit path at the site. In this test, actual system tolerances are used to determine the success or failure of a test. The same external test equipment set up is used.
Bay Level Offset Calibration – continued TX Audit Test The Tests menu item, TX Audit, performs the TX BLO Audit test for a BBX2(s). All measurements are made through the appropriate TX output connector using the calibrated TX cable setup. Prerequisites Before running this test, the following should be done: S S S S CSM–1,GLI2s, BBX2s have correct code load. Primary CSM and MGLI2 are INS. All BBX2s are OOS_RAM. Test equipment and test cables are calibrated and connected for TX BLO calibration.
Bay Level Offset Calibration – continued All Cal/Audit Test The Tests menu item, All Cal/Audit, performs the TX BLO Calibration and Audit test for a XCVR(s). All measurements are made through the appropriate TX output connector using the calibrated TX cable setup. NOTE If the TX calibration portion of the test passed, the BLO data will automatically be downloaded to the BBX2(s) before the audit portion of the test is run.
Bay Level Offset Calibration – continued Create CAL File The Create Cal File function gets the BLO data from BBXs and creates/updates the CAL file for the BTS. If a CAL file does not exist a new one is created. If a CAL file already exists it is updated. After a BTS has been fully optimized a copy of the CAL file must exist so it can be transferred to the CBSC. If TX calibration has been successfully performed for all BBXs and BLO data has been downloaded, a CAL file will exist.
RFDS Setup and Calibration RFDS Description The optional RFDS is a Field Replaceable Unit (FRU) used to perform RF tests of the site from the CBSC or from the LMF. The RFDS contains the following elements: S Antenna Select Unit (ASU) S FWT Interface Card (FWTIC) S Subscriber Unit Assembly (SUA) 3 For complete information regarding the RFDS, refer to the CDMA RFDS Hardware Installation manual (Motorola part no. 6864113A93) CDMA RFDS User’s Guide (Motorola part no.
RFDS Setup and Calibration – continued Table 3-38: RFDS Parameter Settings Step Action * IMPORTANT Log out of the BTS prior to performing this procedure. 1 Using a text editor, verify the following fields are set correctly in the bts–#.cdf file (1 = GLI based RFDS; 2 = Cobra RFDS). EXAMPLE: RfdsEquip = 2 TsuEquip = 1 MC1Equip = 0 MC2Equip = 0 MC3Equip = 0 MC4Equip = 0 Asu1Equip = 1 Asu2Equip = 0 (1 if system is non-duplexed) TestOrigDN = ’123456789’’ NOTE The above is an example of the bts-#.
RFDS Setup and Calibration – continued RFDS TSU NAM Programming The NAM (number assignment module) information needs to be programmed into the TSU before it can receive and process test calls, or be used for any type of RFDS test. The RFDS TSU NAM must be programmed with the appropriate system parameters and phone number during hardware installation. The TSU phone and TSU MSI must be recorded for each BTS used for OMC–R RFDS software configuration.
RFDS Setup and Calibration – continued Valid NAM Ranges Table 3-40 provides the valid NAM field ranges. If any of the fields are missing or out-of–range, the RFDS will error out.
RFDS Setup and Calibration – continued Set Antenna Map Data The antenna map data must be entered manually if an RFDS is installed. Antenna map data does not have to be entered if an RFDS is not installed. The antenna map data is only used for RFDS tests and is required if a RFDS is installed. Prerequisite S Logged into the BTS 3 Table 3-41: Set Antenna Map Data Step Action 1 Click on the Util menu. 2 Select Edit >Antenna Map >TX or RX. A data entry pop–up window will appear.
RFDS Setup and Calibration – continued Set RFDS Configuration Data If an RFDS is installed the RFDS configuration data must be manually entered. Prerequisite S Logged into the BTS IMPORTANT * 3 The entered antenna# index numbers must correspond to the antenna# index numbers used in the antenna maps. Table 3-42: Set RFDS Configuration Data Step Action 1 Click on the Util menu. 2 Select Edit >RFDS Configuration >TX or RX. A data entry pop–up window will appear.
RFDS Setup and Calibration – continued RFDS Calibration The RFDS Calibration option is used to calibrate the RFDS TX and RX paths. For a TX antenna path calibration the BTS XCVR is keyed at a pre–determined power level and the BTS power output level is measured by the RFDS. The power level is then measured at the TX antenna directional coupler by the power measuring test equipment item being used (power meter or analyzer).
RFDS Setup and Calibration – continued Table 3-44: RFDS Calibration Step Action 1 Select the RFDS tab. 2 Click on the RFDS menu. 3 Click on the RFDS Calibration menu item 4 Select the appropriate direction (TX/RX) in the Direction pick list 5 Enter the appropriate channel number(s) in the Channels box. Separate the channel numbers with a comma or a dash if more than one channel number is entered (e.g., 247,585,742 or 385–395 for through).
RFDS Setup and Calibration – continued Program TSU NAM Follow the procedure in Table 3-45 to program the TSU NAM. The NAM must be programmed before it can receive and process test calls, or be used for any type of RFDS test. Prerequisites S MGLI is INS. S TSU is powered up and has a code load. 3 Table 3-45: Program NAM Procedure Step Action 1 Select the RFDS tab. 2 Select the TSU tab. 3 Click on the TSU menu. 4 Click on the Program TSU NAM menu item.
Alarms Testing Alarm Verification The alarms testing should be performed at a convenient point in the optimization/ATP process, since the LMF is necessary to ensure that the SC4812ETL is generating the appropriate alarms. The SC 4812ETL is capable of concurrently monitoring 10 customer defined input signals and four customer defined outputs, which interface to the 50–pin punchblock. All alarms are defaulted to “Not Equipped” during ATP testing.
Alarms Testing – continued Heat Exchanger Alarm Test Table 3-46 gives instructions on testing the Heat Exchanger alarm. Table 3-46: Heat Exchanger Alarm Step 3 Action 1 Turn circuit breaker “B” of the Heat Exchanger circuit breakers OFF. This will generate a Heat Exchanger alarm, ensure that the LMF reports the correct alarm condition. 2 Alarm condition will be reported as BTS Relay #25 – “Heat Exchanger Alarm” makes contact. 3 Turn the circuit breaker “B” ON.
Alarms Testing – continued Minor Alarm Table 3-49 gives instructions on testing minor alarm. Table 3-49: Minor Alarm Step 1 Action Turn the Temperature Compensation Panel (TCP) power switch OFF. This will generate a minor alarm. Verify that the minor alarm LED (amber) is illuminated on the Meter Alarm Panel and the LMF reports this minor alarm. 2 Alarm condition will be reported as BTS Relay #24 “Minor Alarm” makes contact. 3 Turn the TCP power switch ON. The alarm condition should clear.
Alarms Testing – continued Table 3-51: Multiple Rectifier Failure or Major Alarm Step 3 Action 1 With the rectifier module still in the unused shelf position fromTable 3-50 test procedures, turn the AC breaker for the 1st shelf OFF. 2 Verify that a rectifier alarm is generated. Each of the two rectifier modules will illuminate two (2) RED fail LED (DC and Power), and the Meter Alarm Panel and LMF will indicate a major alarm (Rectifier Fail and Major Alarm). The RECTIFIER FAIL LED will illuminate.
Alarms Testing – continued Table 3-53: Multiple Rectifier Failure or Major Alarm Step Action 3 Verify that the LMF reports both alarm conditions. (BTS #29) 4 Turn the AC breaker for this shelf ON. Verify that all alarms have cleared. 5 Return all rectifier module to their original location. This completes the rectifier alarm tests. 3 Battery Over Temperature Alarm (Optional) CAUTION Use special care to avoid damaging insulation on cables, or damaging battery cases when using a power heat gun.
Alarms Testing – continued Figure 3-20: Battery Overtemperature Sensor 3 Buss Bar 6 AWG Cables Battery Overtemp Sensor Negative Temperature Compensation Sensor SC4812ETL0014–1 3-90 SC 4812ETL BTS Optimization/ATP 08/15/2000 PRELIMINARY
Alarms Testing – continued Rectifier Over Temperature Alarm NOTE This is the J8 on the rear of the Meter Alarm Panel itself, this is not connector J8 on the connector bulkhead at the rear of the cabinet. 3 Table 3-55 gives instructions on testing the battery over temperature alarm system. Table 3-55: Rectifier Over Temperature Alarm Step 1 Action Remove the J8 link on the rear of the Meter Alarm Panel (see Figure 3-21 for J8 location).
Alarms Testing – continued Figure 3-21: Location of Connector J8 on the Meter Alarm Panel FRONT VIEW AMP VOLT AMPS VOLT + + – TEST POINTS TEST POINTS 3 PWR – OFF ON REAR VIEW J1 J2 YEL VIOLENT OR J3 J8 J9 J6 J4 J5 Terminal Block RED BLK OR BRWN Terminal Block Rear Connector Panel J4 J5 Not Used J1 J6 J2 J3 Before Leaving the site Table 3-56 gives instructions on what to check before leaving the site.
Chapter 4: Automated Acceptance Test Procedure (ATP) Table of Contents 08/15/2000 Automated Acceptance Test Procedure – Introduction . . . . . . . . . . . . . . . . . . . . Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Prerequisites . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . TX/RX OUT Connections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Table of Contents – continued Notes 4 SC 4812ETL BTS Optimization/ATP 08/15/2000 PRELIMINARY
Automated Acceptance Test Procedure – Introduction Introduction The automated Acceptance Test Procedure (ATP) allows Cellular Field Engineers (CFEs) to run automated acceptance tests on all equipped BTS subsystem devices using the CDMA LMF GUI environment and supported test equipment. The operator can choose to save the results of these tests to a report file, from which ATP reports are generated for later printout. Perform the ATP test on out-of-service sectors or sites only.
Automated Acceptance Test Procedure – Introduction – continued Prerequisites Before attempting to run any ATP tests, all applicable procedures outlined in Chapter 3, Optimization/Calibration, must have been completed successfully (i.e., code load and BLO calibration). NOTE You cannot substitute test equipment with other models not supported by the CDMA LMF. Before attempting to run any ATP tests, ensure the following: S BTS has been optimized and calibrated (see Chapter 3).
Acceptance Tests – Test Set Up Required Test Equipment The following test equipment is required: S LMF S Power meter (used with HP8921A/600 and Advantest R3465) S Communications test set WARNING Before installing any test equipment directly to any TX OUT connector, verify that there are no CDMA channels keyed. At active sites, have the OMCR/CBSC place the carrier assigned to the LPAs under test OOS. Failure to do so can result in serious personal injury and/or equipment damage.
Abbreviated (All–inclusive) Acceptance Tests All–inclusive Tests The all–inclusive acceptance tests are performed from the LMF GUI environment. These tests execute various combinations of individual acceptance tests with a single command. This allows verification of multiple aspects of BTS performance while minimizing time needed for individual test set up and initiation. There are three abbreviated acceptance tests which evaluate different performance aspects of the BTS.
Abbreviated (All–inclusive) Acceptance Tests – continued All TX/RX ATP Test Follow the procedures in Table 4-2 to perform the abbreviated, all–inclusive transmit and receive test. Table 4-2: All TX/RX ATP Test Procedure Step Action 1 Set up the test equipment initially for abbreviated tests per Table 4-1. 2 Select the BBXs and MCCs to be tested. 3 From the Tests menu, select All TX/RX. 4 Select the appropriate carrier(s) (carrier-bts#-sector#-carrier#) displayed in the Channels/Carrier pick list.
Abbreviated (All–inclusive) Acceptance Tests – continued Table 4-3: All TX ATP Test Procedure Step 8 Action Click Save Results or Dismiss. NOTE If Dismiss is used, the test results will not be saved in the test report file. All RX ATP Test Follow the procedures in Table 4-4 to perform the abbreviated, all–inclusive receive test. Table 4-4: All RX ATP Test Procedure 4 Step Action 1 Set up the test equipment for abbreviated tests per Table 4-1. 2 Select the BBXs and MCCs to be tested.
Individual Acceptance Tests–Introduction Individual Acceptance Tests The following individual ATP tests can be used to evaluate specific aspects of BTS operation against individual performance requirements. All testing is performed using the CDMA LMF GUI environment. TX Testing TX tests verify any given transmit antenna path and output power control. All tests are performed using the external calibrated test set. All measurements are via the appropriate TX OUT connector.
Individual Acceptance Tests–Introduction – continued done by verifying that the ratio of PILOT divided by OCNS is equal to 10.2 + 2 dB, and, that the noise floor of all EVEN numbered “OFF” Walsh channels measures < –27 dB (with respect to total CDMA channel power).
TX Spectral Purity Transmit Mask Acceptance Test Background This test verifies the spectral purity of each BBX carrier keyed up at a specific frequency per the current CDF file assignment. All tests are performed using the external calibrated test set controlled by the same command. All measurements are via the appropriate TX OUT connector. The BDC Pilot Gain will be set to to 541 for each antenna, and the forward link will be disabled for all TCH elements from the MCCs.
TX Spectral Purity Transmit Mask Acceptance Test – continued Spectral Purity TX Mask Acceptance Test Follow the steps in Table 4-5 to verify the transmit spectral mask specification on all TX antenna paths using all BBXs equipped at the BTS. Table 4-5: Test Spectral Purity Transmit Mask Step 4 Action 1 Set up the test equipment for TX acceptance tests per Table 4-1. 2 Select the BBXs to be tested. 3 From the Tests menu, select TX Mask.
TX Spectral Purity Transmit Mask Acceptance Test – continued Figure 4-1: TX Mask Verification Spectrum Analyzer Display Mean CDMA Bandwidth Power Reference .
TX Waveform Quality (Rho) Acceptance Test Background This test verifies the transmitted Pilot channel element digital waveform quality of each BBX carrier keyed up at a specific frequency per the current CDF file assignment. All tests are performed using the external calibrated test set controlled by the same command. All measurements are via the appropriate TX OUT connector. The BDC Pilot Gain will be set to to 262 for each antenna, and all TCH elements from the MCCs will be forward link disabled.
TX Pilot Time Offset Acceptance Test Background This test verifies the transmitted Pilot channel element Pilot Time Offset of each BBX carrier keyed up at a specific frequency per the current CDF file assignment. All tests will be performed using the external calibrated test set controlled by the same command. All measurements will be via the TX OUT connector. The BDC Pilot Gain will be set to to 262 for each antenna and all TCH elements from the MCCs will be forward link disabled.
TX Pilot Time Offset Acceptance Tests – continued Table 4-7: Test Pilot Time Offset Step 7 8 Action Follow the cable connection directions as they are displayed. The test results are displayed in the status report window. Click Save Results or Dismiss. NOTE If Dismiss is used, the test results will not be saved in the test report file.
TX Code Domain Power/Noise Floor Acceptance Test Background This test verifies the Code Domain Power and Noise Floor of each BBX carrier keyed up at a specific frequency per the current CDF file assignment. All tests are performed using the external calibrated test set controlled by the same command. All measurements are via the appropriate TX OUT connector.
TX Code Domain Power/Noise Floor Acceptance Test – continued Table 4-8: Test Code Domain Power/Noise Floor Step Action 1 Set up the test equipment for TX acceptance tests per Table 4-1. 2 Select the BBXs and MCCs to be tested. 3 From the Tests menu, select TX Mask. 4 Select the appropriate carrier(s) (carrier-bts#-sector#-carrier#) displayed in the Channels/Carrier pick list. NOTE 4 5 To select multiple items, hold down the Shift or Ctrl key while making the selections.
TX Code Domain Power/Noise Floor Acceptance Test – continued Figure 4-2: Code Domain Analyzer CD Power/Noise Floor Display Examples Pilot Channel PILOT LEVEL MAX OCNS CHANNEL 8.2 dB 12.2 dB MAX OCNS SPEC. Active channels MIN OCNS SPEC. MIN OCNS CHANNEL MAX NOISE FLOOR MAXIMUM NOISE FLOOR: < –27 dB SPEC. Inactive channels Walsh 0 1 2 3 4 5 6 7 ... 4 64 Code Domain Power/Noise Floor (OCNS Pass) Example Pilot Channel PILOT LEVEL FAILURE – EXCEEDS MAX OCNS SPEC. 8.2 dB 12.2 dB MAX OCNS SPEC.
RX FER Acceptance Test Background This test verifies the BTS Frame Erasure Rate (FER) on all Traffic Channel elements currently configured on all equipped MCCs (fullrate at 1% FER) at –119 dBm on the main RX antenna paths. The test is performed on all diversity RX antenna path using only the lowest equipped MCC/CE. All tests are performed using the external calibrated test set as the signal source controlled by the same command. All measurements are via the LMF.
RX FER Acceptance Test – continued FER Acceptance Test Follow the steps in Table 4-9 to verify the FER on all RX antenna paths using all BBXs equipped at the BTS. Table 4-9: Test FER Step Action 1 Set up the test equipment for RX acceptance tests per Table 4-1. 2 Select the BBXs and MCCs to be tested. 3 From the Tests menu, select FER. 4 Select the appropriate carrier(s) (carrier-bts#-sector#-carrier#) displayed in the Channels/Carrier pick list.
Generating an ATP Report Background Each time an ATP test is run, an ATP report is updated and must be saved using the Save Results button to close the status report window. The ATP report will not be updated if the status reports window is closed using the Dismiss button.
Chapter 5: Leaving the Site Table of Contents Updating Calibration Data Files . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Updating CBSC Calibration Data Files . . . . . . . . . . . . . . . . . . . . . . . . . 5-1 5-1 Prepare to Leave the Site . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Removing External Test Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . Reset All Devices and Initialize Site Remotely . . . . . . . . .
Table of Contents – continued Notes 5 SC 4812ETL BTS Optimization/ATP 08/15/2000 PRELIMINARY
Updating Calibration Data Files Updating CBSC Calibration Data Files After completing the TX calibration and audit, updated CAL file information must be moved from the LMF Windows environment back to the CBSC, a Unix environment. The following procedures detail moving files from one environment to the other. Copying CAL files from LMF to a Disk Follow the procedures in Table 5-1 to copy the CAL files from a CDMA LMF computer to a 3.5 diskette.
Back Up Calibration Data Files – continued Table 5-2: Copying CAL Files from Diskette to the CBSC Step 9 Action With Solaris versions of Unix, create a Unix–formatted version of the bts–#.cal file in your home directory by entering the following command: dos2unix /floppy/no_name/bts–#.cal bts–#.cal and press the Enter key (where # is BTS number). NOTE Other versions of Unix do not support the dos2unix command. In these cases, use the Unix cp (copy) command.
Prepare to Leave the Site Removing External Test Equipment Perform the procedure in Table 5-3 to disconnect the test equipment and configure the BTS for active service. Table 5-3: Remove External Test Equipment Step Action 1 Disconnect all external test equipment from all TX and RX connectors on the top of the frame. 2 Reconnect and visually inspect all TX and RX antenna feed lines at the top of the frame.
Prepare to Leave the Site – continued Table 5-5: Bring Modules into Service Step 1 Action In the CDMA LMF GUI environment, select the device(s) you wish to enable. NOTE S The MGLI, CSM, and applicable BDC must be INS before an MCC can be enabled to INS. S Processors which must be enabled and the order of enabling are as follows: – – – – – – MGLI GLI CSMs BDCs MCCs Gateways 2 Click on Device from the menu bar. 3 Click on Enable from the Device menu. A status report window is displayed.
Prepare to Leave the Site – continued Table 5-6: Remove LMF Step Action 6 Disconnect the CDMA LMF terminal Ethernet port from the BTS cabinet. 7 Disconnect the CDMA LMF terminal serial port, the RS–232–to–GPIB interface box, and the GPIB cables as required for equipment transport. Connecting BTS T1 Spans Before leaving the site, connect any T1 span surge suppressors removed previously to allow the LMF to control the BTS. Refer to Table 5-7 and NO TAG as required.
Prepare to Leave the Site – continued Notes 5 5-6 SC 4812ETL BTS Optimization/ATP 08/15/2000 PRELIMINARY
Chapter 6: Basic Troubleshooting Table of Contents 08/15/2000 Basic Troubleshooting Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-1 6-1 Troubleshooting: Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Cannot Log into Cell-Site . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Table of Contents – continued RFDS – Fault Isolation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . All tests fail . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . All RX and TX paths fail . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . All tests fail on a single antenna . . . . . . . . . . . . .
Basic Troubleshooting Overview Overview The information in this chapter addresses some of the scenarios likely to be encountered by Customer Field Engineering (CFE) team members. This troubleshooting guide was created as an interim reference document for use in the field. It provides basic “what to do if” basic troubleshooting suggestions when the BTS equipment does not perform per the procedure documented in the manual.
Troubleshooting: Installation Cannot Log into Cell-Site Table 6-1: Login Failure Troubleshooting Procedures n Step Action 1 If MGLI2 LED is solid RED, it implies a hardware failure. Reset MGLI2 by re-seating it. If this persists, install RGLI2 card in MGLI2 slot and retry. A Red LED may also indicate no Ethernet termination at top of frame. 2 Verify that T1 is disconnected at the Channel Signaling Unit (CSU). If T1 is still connected, verify the CBSC has disabled the BTS. 3 Try ‘ping’ing the MGLI2.
Troubleshooting: Installation – continued Cannot Communicate to Communications Analyzer Table 6-3: Troubleshooting a Communications Analyzer Communication Failure n Step Action 1 Verify analyzer is connected to LMF with GPIB adapter. 2 Verify cable setup. 3 Verify the GPIB address is set to 18. 4 Verify the GPIB adapter DIP switch settings are correct. Refer to Test Equipment setup section for details. 5 Verify the GPIB adapter is not locked up.
Troubleshooting: Download Table 6-4: Troubleshooting Code Download Failure n Step Action 1 Verify T1 is disconnected from the BTS at CSU. 2 Verify LMF can communicate with the BTS device using the Status function. 3 Communication to MGLI2 must first be established before trying to talk to any other BTS device. MGLI2 must be INS_ACT state (green). 4 Verify the card is physically present in the cage and powered-up. 5 If card LED is solid RED, it implies hardware failure.
Troubleshooting: Download – continued Cannot ENABLE Device Before a device can be enabled (placed in-service), it must be in the OOS_RAM state (yellow on the LMF) with data downloaded to the device. The color of the device on the LMF changes to green, once it is enabled.
Troubleshooting: Download – continued LPA Errors Table 6-7: LPA Errors n Step 1 Action If LPAs continue to give alarms, even after cycling power at the circuit breakers, then connect an MMI cable to the LPA and set up a Hyperterminal connection. Enter ALARMS in the Hyperterminal window. The resulting LMF display may provide an indication of the problem. (Call Field Support for further assistance.
Troubleshooting: Calibration Bay Level Offset Calibration Failure Table 6-8: Troubleshooting BLO Calibration Failure n Step 08/15/2000 Action 1 Verify the Power Meter is configured correctly (see the test equipment setup section) and connection is made to the proper TX port. 2 Verify the parameters in the bts–#.
Troubleshooting: Calibration – continued Calibration Audit Failure Table 6-9: Troubleshooting Calibration Audit Failure n Step Action 1 Verify Power Meter is configured correctly (refer to the test equipment setup section). 2 Re-calibrate the Power Meter and verify it is calibrated correctly with cal factors from the power sensor. 3 Verify that no LPA is in alarm state (rapidly flashing red LED). Reset the LPA by pulling the circuit breaker, and, after 5 seconds, pushing back in.
Troubleshooting: Transmit ATP Cannot Perform Txmask Measurement Table 6-10: Troubleshooting TX Mask Measurement Failure n Step Action 1 Verify that TX audit passes for the BBX2(s). 2 If performing manual measurement, verify analyzer setup. 3 Verify that no LPA in the sector is in alarm state (flashing red LED). Re-set the LPA by pulling the circuit breaker, and, after 5 seconds, pushing it back in.
Troubleshooting: Transmit ATP – continued Cannot Perform Code Domain Power and Noise Floor Measurement Table 6-12: Troubleshooting Code Domain Power and Noise Floor Measurement Failure n Step Action 1 Verify presence of RF signal by switching to spectrum analyzer screen. 2 Verify PN offset displayed on analyzer is same as PN offset being used in the CDF file. 3 Disable and re-enable MCC (one or more MCCs based on extent of failure).
Troubleshooting: Receive ATP Multi–FER Test Failure Table 6-14: Troubleshooting Multi-FER Failure n Step Action 1 Verify test equipment set up is correct for a FER test. 2 Verify test equipment is locked to 19.6608 and even second clocks. The yellow LED (REF UNLOCK) must be OFF. 3 Verify MCCs have been loaded with data and are INS–ACT. 4 Disable and re-enable the MCC (1 or more based on extent of failure).
Troubleshooting: CSM Checklist Problem Description Many of the Clock Synchronization Manager (CSM) boards may be resolved in the field before sending the boards to the factory for repair. This section describes known CSM problems identified in field returns, some of which are field-repairable. Check these problems before returning suspect CSM boards. Intermittent 19.
Troubleshooting: CSM Checklist – continued Takes Too Long for CSM to Come INS This may be caused by a delay in GPS acquisition. Check the accuracy flag status and/or current position. Refer to the GSM system time/GPS and LFR/HSO verification section in Chapter 3. At least 1 satellite should be visible and tracked for the “surveyed” mode and 4 satellites should be visible and tracked for the “estimated” mode. Also, verify correct base site position data used in “surveyed” mode.
SCCP Backplane Troubleshooting Introduction The SCCP backplane is a multi–layer board that interconnects all the SCCP modules. The complexity of this board lends itself to possible improper diagnoses when problems occur. Connector Functionality The following connector overview describes the major types of backplane connectors along with the functionality of each. This will allow the Cellular Field Engineer (CFE) to: S Determine which connector(s) is associated with a specific problem type.
SCCP Backplane Troubleshooting – continued GLI2 Ethernet “A” and “B” Connections These BNC connectors are located on the SCCP backplane and routed to the GLI2 board. This interface provides all the control and data communications between the master GLI2 and the other GLI2, between gateways, and for the LMF on the LAN. BBX2 Connector Each BBX2 connector consists of a Harting 2SU/1SU digital connector and two 6–conductor coaxial connectors.
SCCP Backplane Troubleshooting – continued Digital Control Problems No GLI2 Control via LMF (all GLI2s) Table 6-15: No GLI2 Control via LMF (all GLI2s) Step Action 1 Check the Ethernet for proper connection, damage, shorts, or opens. 2 Verify SCCP backplane Shelf ID DIP switch is set correctly. 3 Visually check the master GLI2 connector (both board and backplane) for damage. 4 Replace the master GLI2 with a known good GLI2.
SCCP Backplane Troubleshooting – continued No AMR Control (MGLI2 good) Table 6-18: MGLI2 Control Good – No Control over AMR Step Action 1 Visually check the master GLI2 connector (both board and backplane) for damage. 2 Replace the master GLI2 with a known good GLI2. 3 Replace the AMR with a known good AMR. No BBX2 Control in the Shelf Table 6-19: MGLI2 Control Good – No Control over Co–located GLI2s Step Action 1 Visually check all GLI2 connectors (both board and backplane) for damage.
SCCP Backplane Troubleshooting – continued DC Power Problems WARNING Potentially lethal voltage and current levels are routed to the BTS equipment. This test must be carried out with a second person present, acting in a safety role. Remove all rings, jewelry, and wrist watches prior to beginning this test. No DC Input Voltage to Power Supply Module Table 6-22: No DC Input Voltage to Power Supply Module Step Action 1 Verify DC power is applied to the BTS frame. Verify there are no breakers tripped.
SCCP Backplane Troubleshooting – continued No DC Voltage (+5, +6.5, or +15 Volts) to a Specific GLI2, BBX2, or Switchboard Table 6-23: No DC Input Voltage to any SCCP Shelf Module Step Action 1 Verify steps outlined in Table 6-22 have been performed. 2 Inspect the defective board/module (both board and backplane) connector for damage. 3 Replace suspect board/module with known good board/module.
RFDS – Fault Isolation Introduction The RFDS is used to perform Pre–Calibration Verification and Post-Calibration Audits which limit-check the RFDS-generate and reported receive levels of every path from the RFDS through the directional coupler coupled paths. In the event of test failure, refer to the following tables.
RFDS – Fault Isolation – continued All tests fail on a single antenna If all path failures are on one antenna port, forward and/or reflected, make the following checks. Table 6-27: RFDS Fault Isolation – All tests fail on single antenna path Step Action 1 Visually inspect the site interface cabinet internal cabling to the suspect directional coupler antenna port. 2 Verify the forward and reflected ports connect to the correct RFDS antenna select unit positions on the RFDS backplane.
Module Front Panel LED Indicators and Connectors Module Status Indicators Each of the non-passive plug-in modules has a bi-color (green & red) LED status indicator located on the module front panel. The indicator is labeled PWR/ALM. If both colors are turned on, the indicator is yellow. Each plug-in module, except for the fan module, has its own alarm (fault) detection circuitry that controls the state of the PWR/ALM LED. The fan TACH signal of each fan module is monitored by the AMR.
Module Front Panel LED Indicators and Connectors – continued CSM LED Status Combinations PWR/ALM LED The CSMs include on-board alarm detection. Hardware and software/firmware alarms are indicated via the front panel indicators. After the memory tests, the CSM loads OOS–RAM code from the Flash EPROM, if available. If not available, the OOS–ROM code is loaded from the Flash EPROM. S Solid GREEN – module is INS_ACT or INS_STBY no alarm.
Module Front Panel LED Indicators and Connectors – continued FREQ Monitor Connector A test port provided at the CSM front panel via a BNC receptacle allows monitoring of the 19.6608 MHz clock generated by the CSM. When both CSM 1 and CSM 2 are in an in-service (INS) condition, the CSM 2 clock signal frequency is the same as that output by CSM 1. The clock is a sine wave signal with a minimum amplitude of +2 dBm (800 mVpp) into a 50 Ω load connected to this port.
Module Front Panel LED Indicators and Connectors – continued GLI2 LED Status Combinations The GLI2 module has indicators, controls and connectors as described below and shown in Figure 6-2. The indicators and controls consist of: S Four LEDs S One pushbutton ACTIVE LED Solid GREEN – GLI2 is active. This means that the GLI2 has shelf control and is providing control of the digital interfaces. Off – GLI2 is not active (i.e., Standby). The mate GLI2 should be active.
Module Front Panel LED Indicators and Connectors – continued GLI2 Pushbuttons and Connectors RESET Pushbutton – Depressing the RESET pushbutton causes a partial reset of the CPU and a reset of all board devices. GLI2 will be placed in the OOS_ROM state MMI Connector – The RS–232MMI port connector is intended to be used primarily in the development or factory environment but may be used in the field for debug/maintenance purposes.
Module Front Panel LED Indicators and Connectors – continued BBX2 LED Status Combinations PWR/ALM LED The BBX module has its own alarm (fault) detection circuitry that controls the state of the PWR/ALM LED.
Module Front Panel LED Indicators and Connectors – continued Figure 6-3: MCC24 Front Panel LEDs and LED Indicators PWR/ALM PWR/ALM LED PWR/ALM LENS (REMOVABLE) OFF - operating normally ON - briefly during powerĆup and during failure ąconditions GREEN RED ACTIVE ACTIVE LED RED ACTIVE RAPIDLY BLINKING - Card is codeĆloaded but ąnot enabled SLOW BLINKING - Card is not codeĆloaded ON - card is codeĆloaded and enabled ą(INS_ACTIVE) ON
Basic Troubleshooting – Span Control Link Span Problems (No Control Link) Table 6-28: Troubleshoot Control Link Failure n Step Action 1 Connect the CDMA LMF computer to the MMI port on the applicable MGLI2/GLI2 as shown in Figure 6-4. 2 Start an MMI communication session with the applicable MGLI2/GLI2 by using the Windows desktop shortcut icon (refer to Table 3-11). 3 Once the connection window opens, press the CDMA LMF computer Enter key until the GLI2> prompt is obtained.
Basic Troubleshooting – Span Control Link – continued Figure 6-4: MGLI/GLI Board MMI Connection Detail STATUS LED STATUS RESET ALARM SPANS MASTER MMI ACTIVE To MMI port RESET Pushbutton ALARM LED SPANS LED MASTER LED MMI Port Connector ACTIVE LED 8–PIN NULL MODEM BOARD (TRN9666A) 8–PIN TO 10–PIN RS–232 CABLE (P/N 30–09786R01) 6 CDMA LMF COMPUTER RS–232 CABLE COM1 OR COM2 DB9–TO–DB25 ADAPTER Set BTS Site Span Configuration IMPORTANT * 6-30 Perform the following procedure ONLY if span configur
Basic Troubleshooting – Span Control Link – continued Table 6-29: Set BTS Span Parameter Configuration n Step Action 1 If not previously done, connect the CDMA LMF computer to the MMI port on the applicable MGLI2/GLI2 as shown in Figure 6-4. 2 If there is no MMI communication session in progress with the applicable MGLI2/GLI2, initiate one by using the Windows desktop shortcut icon (refer to Table 3-11).
Basic Troubleshooting – Span Control Link – continued Table 6-29: Set BTS Span Parameter Configuration n Step Action 7 Press the RESET button on the MGLI2/GLI2 for changes to take effect. 8 Return to step 6 of Table 6-28.
A Appendix A: Data Sheets Appendix Content 08/15/2000 Appendix A: Optimization (Pre–ATP) Data Sheets . . . . . . . . . . . . . . . . . . . . . . Verification of Test Equipment Used . . . . . . . . . . . . . . . . . . . . . . . . . . . Site Checklist . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Preliminary Operations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Pre–Power and Initial Power Tests . . . . . . . . . . . . . . . . . . .
A Table of Contents – continued Notes SC 4812ETL BTS Optimization/ATP 08/15/2000 PRELIMINARY
Appendix A: Optimization (Pre–ATP) Data Sheets A Verification of Test Equipment Used Table A-1: Verification of Test Equipment Used Manufacturer Model Serial Number Comments:________________________________________________________ __________________________________________________________________ 08/15/2000 SC 4812ETL BTS Optimization/ATP PRELIMINARY A-1
A Appendix A: Optimization (Pre–ATP) Data Sheets – continued Site Checklist Table A-2: Site Checklist OK Parameter Specification Comments - Deliveries Per established procedures - Floor Plan Verified - Inter Frame Cables: Ethernet Frame Ground Power Per procedure Per procedure Per procedure - Factory Data: BBX2 Test Panel RFDS Per procedure Per procedure Per procedure - Site Temperature - Dress Covers/Brackets Preliminary Operations Table A-3: Preliminary Operations OK Parameter Spe
Appendix A: Optimization (Pre–ATP) Data Sheets – continued A Pre–Power and Initial Power Tests Table A3a: Pre–power Checklist OK - Parameter Specification Pre–power–up tests Verify power supply output voltage at the top of each BTS frame is within specifications - Internal Cables: ISB (all cages) CSM (all cages) Power (all cages) Ethernet Connectors LAN A ohms LAN B ohms LAN A shield LAN B shield Ethernet Boots - Air Impedance Cage (single cage) installed - Initial power–up tests Verify power
A Appendix A: Optimization (Pre–ATP) Data Sheets – continued General Optimization Checklist Table A3b: Pre–power Checklist OK Parameter Specification - LEDs Frame fans illuminated operational - LMF to BTS Connection Preparing the LMF Log into the LMF PC Create site specific BTS directory Download device loads per procedure per procedure per procedure per procedure - Ping LAN A Ping LAN B per procedure per procedure - Download/Enable MGLI2s Download/Enable GLI2s Set Site Span Configuration Dow
Appendix A: Optimization (Pre–ATP) Data Sheets – continued A GPS Receiver Operation Table A-4: GPS Receiver Operation OK Parameter Specification - GPS Receiver Control Task State: tracking satellites Verify parameter - Initial Position Accuracy: Verify Estimated or Surveyed - Current Position: lat lon height RECORD in msec and cm also convert to deg min sec - Current Position: satellites tracked Estimated: (>4) satellites tracked,(>4) satellites visible Surveyed: (>1) satellite tracked,(>4)
A Appendix A: Optimization (Pre–ATP) Data Sheets – continued LFR Receiver Operation Table A-5: LFR Receiver Operation OK Parameter Specification - Station call letters M X Y Z assignment.
Appendix A: Optimization (Pre–ATP) Data Sheets – continued A LPA IM Reduction Table A-6: LPA IM Reduction Parameter OK Comments CARRIER LPA # 2:1 3–Sector BP 3–Sector Specification - 1A C1 C1 No Alarms - 1B C1 C1 No Alarms - 1C C1 C1 No Alarms - 1D C1 C1 No Alarms - 3A C2 C2 No Alarms - 3B C2 C2 No Alarms - 3C C2 C2 No Alarms - 3D C2 C2 No Alarms Comments:_________________________________________________________ 08/15/2000 SC 4812ETL BTS Optimization/ATP P
A Appendix A: Optimization (Pre–ATP) Data Sheets – continued TX Bay Level Offset / Power Output Verification for 3–Sector Configurations 1–Carrier 2–Carrier Non–adjacent Channels Table A-7: TX BLO Calibration (3–Sector: 1–Carrier, 2–Carrier and 4–Carrier Non–adjacent Channels) OK Parameter Specification Comments BBX2–1, ANT–1 = BBX2–r, ANT–1 = dB dB BBX2–2, ANT–2 = BBX2–r, ANT–2 = dB dB - BBX2–3, ANT–3 = BBX2–r, ANT–3 = dB dB - BBX2–7, ANT–1 = BBX2–r, ANT–1 = dB dB BBX2–8, ANT–2 = BBX2–r, AN
Appendix A: Optimization (Pre–ATP) Data Sheets – continued A 2–Carrier Adjacent Channel Table A-8: TX Bay Level Offset Calibration (3–Sector: 2–Carrier Adjacent Channels) OK Parameter Specification Comments BBX2–1, ANT–1 = BBX2–r, ANT–1 = dB dB BBX2–2, ANT–2 = BBX2–r, ANT–2 = dB dB - BBX2–3, ANT–3 = BBX2–r, ANT–3 = dB dB - BBX2–7, ANT–4 = BBX2–r, ANT–4 = dB dB BBX2–8, ANT–5 = BBX2–r, ANT–5 = dB dB - BBX2–9, ANT–6 = BBX2–r, ANT–6 = dB dB - BBX2–1, ANT–1 = BBX2–r, ANT–1 = dB dB BBX2–2,
A Appendix A: Optimization (Pre–ATP) Data Sheets – continued TX Antenna VSWR Table A-9: TX Antenna VSWR OK Parameter Specification - VSWR – Antenna A1 < (1.5 : 1) - VSWR – Antenna A2 < (1.5 : 1) - VSWR – Antenna A3 < (1.5 : 1) - VSWR – Antenna B4 < (1.5 : 1) - VSWR – Antenna B5 < (1.5 : 1) - VSWR – Antenna B6 < (1.
Appendix A: Optimization (Pre–ATP) Data Sheets – continued A RX Antenna VSWR Table A-10: RX Antenna VSWR OK Parameter Specification - VSWR – Antenna A1 < (1.5 : 1) - VSWR – Antenna A2 < (1.5 : 1) - VSWR – Antenna A3 < (1.5 : 1) - VSWR – Antenna B4 < (1.5 : 1) - VSWR – Antenna B5 < (1.5 : 1) - VSWR – Antenna BXC6 < (1.
A Appendix A: Optimization (Pre–ATP) Data Sheets – continued Notes A-12 SC 4812ETL BTS Optimization/ATP 08/15/2000 PRELIMINARY
Appendix A: Site Serial Number Check List A Date Site SCCP Shelf Site I/O A & B SCCP Shelf CSM–1 CSM–2 HSO CCD–1 CCD–2 AMR–1 AMR–2 MPC–1 MPC–2 Fans 1–3 GLI2–1 GLI2–2 BBX2–1 BBX2–2 BBX2–3 BBX2–4 BBX2–5 BBX2–6 BBX2–R1 MCC24–1 MCC24–2 MCC24–3 MCC24–4 CIO SWITCH PS–1 PS–2 PS–3 08/15/2000 SC 4812ETL BTS Optimization/ATP PRELIMINARY A-13
A Appendix A: Site Serial Number Check List – continued LPAs LPA 1A LPA 1B LPA 1C LPA 1D LPA 3A LPA 3B LPA 3C LPA 3D A-14 SC 4812ETL BTS Optimization/ATP 08/15/2000 PRELIMINARY
Appendix B: FRU Optimization/ATP Test Matrix Appendix Content Appendix B: FRU Optimization/ATP Test Matrix . . . . . . . . . . . . . . . . . . . . . . . Usage & Background . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Detailed Optimization/ATP Test Matrix . . . . . . . . . . . . . . . . . . . . . . . .
Table of Contents – continued Notes B SC 4812ETL BTS Optimization/ATP 08/15/2000 PRELIMINARY
Appendix B: FRU Optimization/ATP Test Matrix Usage & Background Periodic maintenance of a site may also may mandate re–optimization of specific portions of the site. An outline of some basic guidelines is included in the following tables. IMPORTANT * Re–optimization steps listed for any assembly detailed in the tables below must be performed anytime a RF cable associated with it is replaced.
Appendix B: FRU Optimization/ATP Test Matrix – continued Inter-frame Cabling Optimization must be performed after the replacement of any RF cabling between BTS frames. B Table B-2: When to Optimize Inter–frame Cabling Item Replaced Optimize: Expansion frame to BTS frame (RX) cables The affected sector/antenna RX paths. BTS frame to expansion frame (TX) cables The affected sector/antenna TX paths.
Appendix B: FRU Optimization/ATP Test Matrix – continued original slots, and re–downloaded (code and BLO data). RX and TX calibration audits should then be performed.
Appendix B: FRU Optimization/ATP Test Matrix – continued NO TAG/ NO TAG NO TAG/ NO TAG Table 3-16 D D D D D LPA Combiner Filter 2:1 D SWITCH CARD GPS D Power Converters (See Note) LFR/HSO D LPA Filter Bandpass CSM D GLI2 MCC24 D LPA BBX2 D SCCP Backplane D CIO Initial Power-up D TX Cables Table 2-6 D Multicoupler/Preselector Table 2-1 Initial Boards/Modules Install, Preliminary Operations, CDF Site Equipage; etc.
Appendix C: BBX Gain Set Point vs. BTS Output Considerations Appendix Content C Usage & Background . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Table of Contents – continued Notes C SC 4812ETL BTS Optimization/ATP 08/15/2000 PRELIMINARY
Appendix C: BBX2 Gain Set Point vs. BTS Output Considerations Usage & Background Table C-1 outlines the relationship between the total of all code domain channel element gain settings (digital root sum of the squares) and the BBX2 Gain Set Point between 33.0 dBm and 44.0 dBm. The resultant RF output (as measured at the top of the BTS in dBm) is shown in the table. The table assumes that the BBX2 Bay Level Offset (BLO) values have been calculated.
Appendix C: BBX2 Gain Set Point vs. BTS Output Considerations – continued Table C-1: BBX2 Gain Set Point vs. Actual BTS Output (in dBm) dBm' Gainb 44 43 42 41 40 39 38 37 36 35 34 33 381 – – – – 43.3 42.3 41.3 40.3 39.3 38.3 37.3 36.3 374 – – – – 43.1 42.1 41.1 40.1 39.1 38.1 37.1 36.1 366 – – – – 42.9 41.9 40.9 39.9 38.9 37.9 36.9 35.9 358 – – – – 42.7 41.7 40.7 39.7 38.7 37.7 36.7 35.7 350 – – – 43.5 42.5 41.5 40.5 39.5 38.5 37.
Appendix D: CDMA Operating Frequency Information Appendix Content 08/15/2000 1900 MHz PCS Channels . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . D-1 Calculating 1900 MHz Center Frequencies . . . . . . . . . . . . . . . . . . . . . . . . . . . . D-2 800 MHz CDMA Channels . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . D-4 Calculating 800 MHz Center Frequencies . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Table of Contents – continued Notes D SC 4812ETL BTS Optimization/ATP 08/15/2000 PRELIMINARY
CDMA Operating Frequency Programming Information – North American PCS Bands Introduction Programming of each of the BTS BBX2 synthesizers is performed by the BTS GLI2s via the CHI bus. This programming data determines the transmit and receive transceiver operating frequencies (channels) for each BBX2. 1900 MHz PCS Channels Figure D-1 shows the valid channels for the North American PCS 1900 MHz frequency spectrum.
CDMA Operating Frequency Programming Information – North American Bands – continued Calculating 1900 MHz Center Frequencies Table D-1 shows selected 1900 MHz CDMA candidate operating channels, listed in both decimal and hexadecimal, and the corresponding transmit, and receive frequencies. Center frequencies (in MHz) for channels not shown in the table may be calculated as follows: S TX = 1930 + 0.05 * Channel# Example: Channel 262 TX = 1930 + 0.05*262 = 1943.
CDMA Operating Frequency Programming Information – North American Bands – continued Table D-1: 1900 MHz TX and RX Frequency vs. Channel Channel Number Decimal Hex 600 0258 625 0271 650 028A 675 02A3 700 02BC 725 02D5 750 02EE 775 0307 800 0320 825 0339 850 0352 875 036B 900 0384 925 039D 950 03B6 975 03CF 1000 03E8 1025 0401 1050 041A 1075 0433 1100 044C 1125 0465 1150 047E 1175 0497 08/15/2000 Transmit Frequency (MHz) Center Frequency 1960.00 1961.25 1962.50 1963.75 1965.00 1966.25 1967.50 1968.75 1970.
CDMA Operating Frequency Programming Information – North American Bands – continued 800 MHz CDMA Channels Figure D-2 shows the valid channels for the North American cellular telephone frequency spectrum. There are 10 CDMA wireline or non–wireline band channels used in a CDMA system (unique per customer operating system). 848.970 893.970 777 739 716 717 694 689 666 667 644 356 333 334 311 799 846.480 846.510 891.480 891.510 889.980 890.010 844.980 845.010 879.990 880.020 834.990 835.
CDMA Operating Frequency Programming Information – North American Bands – continued Table D-2: 800 MHz TX and RX Frequency vs. Channel Channel Number Decimal Hex Transmit Frequency (MHz) Center Frequency Receive Frequency (MHz) Center Frequency 50 0032 871.5000 826.5000 75 004B 872.2500 827.2500 100 0064 873.0000 828.0000 125 007D 873.7500 828.7500 150 0096 874.5000 829.5000 175 00AF 875.2500 830.2500 200 00C8 876.0000 831.0000 225 00E1 876.7500 831.7500 250 00FA 877.
CDMA Operating Frequency Programming Information – North American Bands – continued Notes D D-6 08/15/2000 PRELIMINARY SC 4812ETL BTS Optimization/ATP
Appendix E: PN Offset/I & Q Offset Register Programming Information Appendix Content PN Offset Background . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . E-1 PN Offset Usage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Table of Contents – continued Notes E SC 4812ETL BTS Optimization/ATP 08/15/2000 PRELIMINARY
Appendix E: PN Offset Programming Information PN Offset Background All channel elements transmitted from a BTS in a particular 1.25 MHz CDMA channel are orthonogonally spread by 1 of 64 possible Walsh code functions; additionally, they are also spread by a quadrature pair of PN sequences unique to each sector. Overall, the mobile uses this to differentiate multiple signals transmitted from the same BTS (and surrounding BTS) sectors, and to synchronize to the next strongest sector.
Appendix E: PN Offset Programming Information – continued IMPORTANT * If the wrong I and Q values are used with the wrong FineTxAdj parameter, system timing problems will occur. This will cause the energy transmitted to be “smeared” over several Walsh codes (instead of the single Walsh code that it was assigned to), causing erratic operation. Evidence of smearing is usually identified by Walsh channels not at correct levels or present when not selected in the Code Domain Power Test.
Appendix E: PN Offset Programming Information – continued Table E-1: PnMaskI and PnMaskQ Values for PilotPn Pilot PN 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 I 14–Chip Delay Q I Q (Dec.) (Hex.
Appendix E: PN Offset Programming Information – continued Table E-1: PnMaskI and PnMaskQ Values for PilotPn Pilot PN E 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 I 14–Chip Delay Q I Q (Dec.) (Hex.
Appendix E: PN Offset Programming Information – continued Table E-1: PnMaskI and PnMaskQ Values for PilotPn Pilot PN 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143 144 145 146 147 148 149 150 I 14–Chip Delay Q I Q (Dec.) (Hex.
Appendix E: PN Offset Programming Information – continued Table E-1: PnMaskI and PnMaskQ Values for PilotPn Pilot PN E 151 152 153 154 155 156 157 158 159 160 161 162 163 164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183 184 185 186 187 188 189 190 191 192 193 194 195 196 197 198 199 200 I 14–Chip Delay Q I Q (Dec.) (Hex.
Appendix E: PN Offset Programming Information – continued Table E-1: PnMaskI and PnMaskQ Values for PilotPn Pilot PN 201 202 203 204 205 206 207 208 209 210 211 212 213 214 215 216 217 218 219 220 221 222 223 224 225 226 227 228 229 230 231 232 233 234 235 236 237 238 239 240 241 242 243 244 245 246 247 248 249 250 I 14–Chip Delay Q I Q (Dec.) (Hex.
Appendix E: PN Offset Programming Information – continued Table E-1: PnMaskI and PnMaskQ Values for PilotPn Pilot PN E 251 252 253 254 255 256 257 258 259 260 261 262 263 264 265 266 267 268 269 270 271 272 273 274 275 276 277 278 279 280 281 282 283 284 285 286 287 288 289 290 291 292 293 294 295 296 297 298 299 300 I 14–Chip Delay Q I Q (Dec.) (Hex.
Appendix E: PN Offset Programming Information – continued Table E-1: PnMaskI and PnMaskQ Values for PilotPn Pilot PN 301 302 303 304 305 306 307 308 309 310 311 312 313 314 315 316 317 318 319 320 321 322 323 324 325 326 327 328 329 330 331 332 333 334 335 336 337 338 339 340 341 342 343 344 345 346 347 348 349 350 I 14–Chip Delay Q I Q (Dec.) (Hex.
Appendix E: PN Offset Programming Information – continued Table E-1: PnMaskI and PnMaskQ Values for PilotPn Pilot PN E 351 352 353 354 355 356 357 358 359 360 361 362 363 364 365 366 367 368 369 370 371 372 373 374 375 376 377 378 379 380 381 382 383 384 385 386 387 388 389 390 391 392 393 394 395 396 397 398 399 400 I 14–Chip Delay Q I Q (Dec.) (Hex.
Appendix E: PN Offset Programming Information – continued Table E-1: PnMaskI and PnMaskQ Values for PilotPn Pilot PN 401 402 403 404 405 406 407 408 409 410 411 412 413 414 415 416 417 418 419 420 421 422 423 424 425 426 427 428 429 430 431 432 433 434 435 436 437 438 439 440 441 442 443 444 445 446 447 448 449 450 I 14–Chip Delay Q I Q (Dec.) (Hex.
Appendix E: PN Offset Programming Information – continued Table E-1: PnMaskI and PnMaskQ Values for PilotPn Pilot PN E 451 452 453 454 455 456 457 458 459 460 461 462 463 464 465 466 467 468 469 470 471 472 473 474 475 476 477 478 479 480 481 482 483 484 485 486 487 488 489 490 491 492 493 494 495 496 497 498 499 500 I 14–Chip Delay Q I Q (Dec.) (Hex.
Appendix E: PN Offset Programming Information – continued Table E-1: PnMaskI and PnMaskQ Values for PilotPn Pilot PN 501 502 503 504 505 506 507 508 509 510 511 I 14–Chip Delay Q I Q (Dec.) (Hex.) 14301 23380 11338 2995 23390 14473 6530 20452 12226 1058 12026 19272 29989 8526 18139 3247 28919 7292 20740 27994 2224 6827 37DD 5B54 2C4A 0BB3 5B5E 3889 1982 4FE4 2FC2 0422 2EFA 4B48 7525 214E 46DB 0CAF 70F7 1C7C 5104 6D5A 08B0 1AAB I 13–Chip Delay Q I Q (Dec.) (Hex.
Appendix E: PN Offset Programming Information – continued Notes E E-14 SC 4812ETL BTS Optimization/ATP 08/15/2000 PRELIMINARY
Appendix F: Test Equipment Preparation Appendix Content 08/15/2000 Test Equipment Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Purpose . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . HP8921A Test Equipment Connections . . . . . . . . . . . . . . . . . . . . . . . . HP8921A System Connectivity Test . . . . . . . . . . . . . . . . . . . . . . . . . . . Setting HP8921A and HP83236A/B GPIB Address . . . . . . . .
Table of Contents – continued Notes F 08/15/2000 PRELIMINARY SC 4812ETL BTS Optimization/ATP
Test Equipment Preparation Purpose This appendix provides information on setting up the HP8921 with PCS interface, the HP8935 and the Advantest R3465. The Cybertest test set doesn’t require any setup. HP8921A Test Equipment Connections The following diagram depicts the rear panels of the HP 8921A test equipment as configured to perform automatic tests. All test equipment is controlled by the LMF via an IEEE–488/GPIB bus.
Test Equipment Preparation – continued Figure F-1: HP8921A/600 Cables Connection for 10 MHz Signal and GPIB without Rubidium Reference HP83203B CDMA CELLULAR ADAPTER TO POWER METER GPIB CONNECTOR ÌÌÌÌÌÌÌÌÌ ÌÌÌÌÌÌÌÌÌ ÌÌÌÌÌÌÌÌÌ ÌÌÌÌÌÌÌÌÌ ÌÌÌÌÌÌÌÌÌ TO GPIB INTERFACE BOX HP8921A CELL SITE TEST SET HP83236A PCS INTERFACE F REF IN HP–IB FW00368 REAR PANEL COMMUNICATIONS TEST SET F-2 SC 4812ETL BTS Optimization/ATP 08/15/2000 PRELIMINARY
Test Equipment Preparation – continued Figure F-2 shows the connections when using an external 10 MHz Rubidium reference. Table F-2: HP8921A/600 Communications Test Set Rear Panel Connections With Rubidium Reference From Test Set: 8921A CW RF OUT 114.3 MHZ IF OUT IQ RF IN DET OUT CONTROL I/O 10 MHZ OUT HPIB INTERFACE 10 MHZ INPUT To Interface: 83203B CDMA Connector Type 83236A PCS CW RF IN 114.
Test Equipment Preparation – continued Figure F-2: HP8921A Cables Connection for 10 MHz Signal and GPIB with Rubidium Reference 10 MHZ WITH RUBIDIUM STANDARD HP83203B CDMA CELLULAR ADAPTER TO POWER METER GPIB CONNECTOR ÌÌÌÌÌÌÌÌ ÌÌÌÌÌÌÌÌ ÌÌÌÌÌÌÌÌ ÌÌÌÌÌÌÌÌ ÌÌÌÌÌÌÌÌ TO GPIB INTERFACE BOX HP8921A CELL SITE TEST SET F HP83236A PCS INTERFACE REF IN HP–IB FW00369 REAR PANEL COMMUNICATIONS TEST SET F-4 SC 4812ETL BTS Optimization/ATP 08/15/2000 PRELIMINARY
Test Equipment Preparation – continued HP8921A System Connectivity Test Follow the steps outlined in Table F-3 to verify that the connections between the PCS Interface and the HP8921A are correct and cables are intact. The software also performs basic functionality checks of each instrument. IMPORTANT * Disconnect other GPIB devices, especially system controllers, from the system before running the connectivity software.
Test Equipment Preparation – continued Setting HP8921A and HP83236A/B GPIB Address Table F-4: Setting HP8921A GPIB Address Step Action 1 If you have not already done so, turn the HP8921A power on. 2 Verify that the GPIB addresses are set correctly. S HP8921A HP–IB Adrs = 18, accessed by pushing LOCAL and selecting More and I/O Configure on the HP8921A/600. (Consult test equipment OEM documentation for additional info as required). S HP83236A (or B) PCS Interface GPIB address=19.
Test Equipment Preparation – continued Advantest R3465 Connection The following diagram depicts the rear panels of the Advantest test equipment as configured to perform automatic tests. All test equipment is controlled by the LMF via an IEEE–488/GPIB bus. The LMF expects each piece of test equipment to have a factory-set GPIB address (refer to Table F-7).
Test Equipment Preparation – continued Figure F-4 shows the connections when using an external 10 MHz Rubidium reference.
Test Equipment Preparation – continued R3465 GPIB Address & Clock setup Table F-7 describes the steps to set the GPIB address and clock for the Advantest R3465 equipment. Table F-7: Advantest R3465 GPIB Address and Clock Setup Step 1 Action Communications test set GPIB address=18 (perform the following to view/set as required) Perform the following to set the standard parameters on the test set: S Push the SHIFT then PRESET pushbutton (just below the CRT display).
Manual Cable Calibration Calibrating Test Cable Setup using HP PCS Interface (HP83236) Table F-9 covers the procedure to calibrate the test equipment using the HP8921 Cellular Communications Analyzer equipped with the HP83236 PCS Interface. NOTE This calibration method must be executed with great care. Some losses are measured close to the minimum limit of the power meter sensor (–30 dBm).
Manual Test Cable Setup – continued Table F-9: Calibrating Test Cable Setup (using the HP PCS Interface) Step Action 8 Set RF Generator level: – Position the cursor at RF Generator Level and select it. – Enter –10 using the numeric keypad; press [Enter] and the screen will go blank. – When the screen reappears, the value –10 dBm will be displayed on the RF Generator Level line.
Manual Test Cable Setup – continued Table F-9: Calibrating Test Cable Setup (using the HP PCS Interface) Step Action 19 After all components are calibrated, reassemble all components together and calculate the total test setup loss by adding up all the individual losses: S Example: Total test setup loss = –1.4 –29.8 –20.1 = –51.3 dB. This calculated value will be used in the next series of tests. 20 Under Screen Controls press the TESTS button to display the TESTS (Main Menu) screen.
Manual Test Cable Setup – continued Figure F-5: Cable CalibrationUsing HP8921 with PCS Interface MEMORY CARD SLOT POWER SENSOR (A) (A) POWER SENSOR (B) F (B) 20 dB / 20 WATT ATTENUATOR POWER SENSOR (C) POWER SENSOR (C) 150 W NON–RADIATING RF LOAD 08/15/2000 30 dB DIRECTIONAL COUPLER FW00292 SC 4812ETL BTS Optimization/ATP PRELIMINARY F-13
Manual Test Cable Setup – continued Calibrating Test Cable Setup using Advantest R3465 NOTE Be sure the GPIB Interface is OFF for this procedure. Advantest R3465 Manual Test setup and calibration must be performed at both the TX and RX frequencies. Table F-10: Procedure for Calibrating Test Cable Setup Using Advantest R3465 Step Action * IMPORTANT – This procedure can only be performed after test equipment has been allowed to warm–up and stabilize for a minimum of 60 minutes.
Manual Test Cable Setup – continued Table F-10: Procedure for Calibrating Test Cable Setup Using Advantest R3465 Step 16 Action Disconnect the power meter sensor from the R3561L RF OUT jack. * IMPORTANT The Power Meter sensor’s lower limit is –30 dBm. Thus, only components having losses < 30 dB should be measured using this method. For best accuracy, always re–zero the power meter before connecting the power sensor to the component being calibrated.
Manual Test Cable Setup – continued Figure F-6: Cable Calibration using Advantest R3465 RF OUT POWER SENSOR (A) & (B) POWER SENSOR F (C) 20 DB / 2 WATT ATTENUATOR POWER SENSOR (C) POWER SENSOR (D) 100 W NON–RADIATING RF LOAD F-16 FW00320 30 DB DIRECTIONAL COUPLER SC 4812ETL BTS Optimization/ATP 08/15/2000 PRELIMINARY
Manual Test Cable Setup – continued Calibrating HP 437 Power Meter Precise transmit output power calibration measurements are made using a bolometer–type broadband power meter with a sensitive power sensor. Follow the steps outlined in Table F-11 to enter information unique to the power sensor before calibrating the test setup. Refer to Figure F-7 as required. IMPORTANT * This procedure must be done in conjunction with the automated calibration to enter power sensor specific calibration values.
Manual Test Cable Setup – continued Table F-11: Power Meter Calibration Procedure Step 4 Action Perform the following to set or verify the correct power sensor model: – Press [SHIFT] then [a] to select SENSOR. – Identify the power sensor model number from the sensor label. Use the [y] or [b] button to select the appropriate model; then press [ENTER]. NOTE Be sure the PWR REF (power reference) output is OFF (observe that the triangular indicator is NOT displayed as shown in Step 7).
Manual Test Cable Setup – continued Calibrating Gigatronics 8542 power meter Precise transmit output power calibration measurements are made using a bolometer–type broadband power meter with a sensitive power sensor. Follow the steps in Table F-12 to enter information unique to the power sensor. Table F-12: Calibrate Gigatronics 8542 Power Meter Step Action ! CAUTION Do not connect/disconnect the power meter sensor cable with AC power applied to the meter.
Manual Test Cable Setup – continued Figure F-8: Gigatronics 8542C Power Meter Detail CONNECT POWER SENSOR TO CALIBRATOR POWER REFERENCE WHEN CALIBRATING/ZEROING UNIT CONNECT POWER SENSOR WITH POWER METER TURNED OFF AC POWER FRONT View GPIB CONNECTION REAR View FW00564 F F-20 SC 4812ETL BTS Optimization/ATP 08/15/2000 PRELIMINARY
Appendix G: Download ROM Code Appendix Content Downloading ROM Code with the LMF . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Exception Procedure – Downloading Device ROM Code . . . . . . . . . .
Table of Contents – continued Notes F SC 4812ETL BTS Optimization/ATP 08/15/2000 PRELIMINARY
Downloading ROM Code with the LMF Exception Procedure – Downloading Device ROM Code This procedure is not part of a normal optimization. Perform this procedure only on an exception basis when no alternative exists to load a BTS device with the correct version of ROM code. NOTE An MGLI or GLI must be INS (green) before ROM code can be downloaded to non–GLI devices. WARNING Release 2.9.x RAM code must NOT be downloaded to a device loaded with Release 2.8.x ROM code, and Release 2.8.
Downloading ROM Code with the LMF – continued CAUTION The Release level of the ROM code to be downloaded must be the same as the Release level of the ROM code resident in the other devices in the BTS. Release 2.9.x ROM code must not be downloaded to a frame having Release 2.8.x code, and Release 2.8.x code must not be downloaded to a frame having Release 2.9.x code. This procedure should only be used to upgrade replacement devices for a BTS. It should NOT be used to upgrade all devices in a BTS.
Downloading ROM Code with the LMF – continued Table G-1: Download ROM and RAM Code to Devices Step Action ! CAUTION A ROM code file with the correct hardware binary type (HW Bin Type) must be chosen. Using a file with the wrong HW Bin Type can result in unpredictable operation and damage to the device. 9 Click on the ROM code file with the filename which matches the device type and HW Bin Type number noted in step 3 (e.g., file bbx_rom.bin.0604 is the ROM code file for a BBX with a HW Bin Type of 0604).
Downloading ROM Code with the LMF – continued Notes F G-4 SC 4812ETL BTS Optimization/ATP 08/15/2000 PRELIMINARY
Index Numbers 10 MHz Rubidium Standard, optional test equipment, 1-11 10BaseT/10Base2 converter LMF to BTS connection, 3-20 remove from BTS, 5-4 2–way splitter, optional test equipment, 1-10 A Abbreviated RX acceptance test, all–inclusive, 4-4 TX acceptance test, all–inclusive, 4-4 code domain noise floor acceptance test procedure, 4-16 code domain power acceptance test procedure, 4-16 failure report generation, 4-20 FER test, frame error rate testing, 4-19 pilot time offset, 4-13 prerequisites, 4-2 spec
Index – continued RX sensitivity/frame error rate, 4-8 system software download, 3-3 when to optimize, B-1 cbsc folder, 3-17 CCD, 1-18 CDF site configuration, 3-2 site equipage verification, 3-3 site type and equipage data information, 2-1 BTS Frame Erasure Rate.
Index – continued D F data Folder, 3-18 Failure report generation, 4-20 DC Power Pre–test (BTS Frame), 2-7 FER, acceptance test, 4-19 DC Power Problems, C–CCP Backplane Troubleshooting, 6-18 Files calibration data file, BLO, 3-66 intermediate file, 4-20 DC/DC Converter LED Status Combinations, 6-22 Detailed, optimization/ATP test matrix, B-2 Filtronics, low IM Duplexer (Cm035–f2) or equivalent, optional test equipment, 1-10 Devices, download.
Index – continued HP 83236A, F-5 loads folder, 3-17 HP 8921A/600 test set, 1-8 Local Maintenance Facility.
Index – continued O test data sheets, A-2 Online Help, 3-27 Optional test equipment, 1-10 10 MHz rubidium standard, 1-11 2–way splitter, 1-10 CDMA subscriber mobile or portable radiotelephone, 1-10 duplexer, 1-10 frequency counter, 1-10 LAN tester, 1-10 oscilloscope, 1-10 RF circular, 1-11 RF test cable, 1-10 spectrum analyzer, 1-10 Prepare to leave site connect BTS T1 spans, 5-5 remove external test equipment, 5-3 Prepare to leave the site bringing modules into service, 5-3 download code and data from
Index – continued test cable, 1-9 site equippage, CDF file, 3-2 RF Path Bay Level Offset Calibration, 3-64 Site expansion, 1-4 RFDS – Fault Isolation, 6-20 Span line T1/E1 verification equipment, 1-10 troubleshooting, 6-29 RFDS Calibration, 3-82 RFDS Location, SC 4812ET, 1-21 Span line configuration, troubleshooting, 6-30 RFDS Test Subscriber Unit, 3-31 Span Line connector , 6-14 RFDS TSU Calibration Channel Frequencies, 3-82 Rho TX waveform quality acceptance test, 4-12 waveform quality require
Index – continued Test Equipment Setup, 3-47 Test Equipment Setup Calibration for TX Bay Level Offset, 3-61, F-14 TX and RX Signal Routing, C–CCP Backplane Troubleshooting, 6-19 TX Audit Test, 3-73 TX Bay Level Offset and TX ATP test equipment setup calibration, 3-60 Test Equipment Setup Chart, 3-48 Test equipment setup RF path calibration, 3-68 tx fine adjust, E-1 Test Set Calibration, 3-55 TX Path Calibration, 3-65 Timing reference cables, required test equipment Model SGLN1145A/4132A CSMs, 1-9 Mo
Index – continued Notes Index-8 SC 4812ETL BTS Optimization/ATP 08/15/2000 PRELIMINARY