Automated Acceptance Test Procedure – All–inclusive TX & RX – continued
PRELIMINARY 2
SC 4812ET BTS Optimization/ATP – CDMA LMF
July 1999
4-8
Full Optimization Test
The LMF Tests menu list item, Full Optimization, performs all
optimization tests for all BBX2(s) and MCC(s). All measurements are
made through the appropriate TX and RX output connectors using the
calibrated TX and RX cable setups.
Tests performed include:
Calibrate all selected BBX2s
Load and audit BLO
Perform All TX ATP on all selected BBX2s and MCCs
Perform All RX ATP on all selected BBX2s and MCCs
Prerequisites
Before attempting to run any ATP tests, ensure the following have been
completed:
CSMs, GLI2s, BBX2s, and MCCs have correct code load and data
load
Primary CSM, GLI, and MCCs are INS
BTS has been Optimized and Calibrated
BBX2s are OOS-RAM
Test equipment is connected for ATP tests (see Figure 3-16 through
Figure 3-19).
Test equipment is warmed up 60 minutes and calibrated
Test cables are calibrated
GPIB is on
LMF is logged into the BTS
4