Automated Acceptance Test Procedure – All–inclusive TX & RX – continued
PRELIMINARY 2
SC 4812ET BTS Optimization/ATP – CDMA LMF
July 1999
4-4
All-RX ATP Test
The CDMA LMF Tests menu list item, All RX, performs all receive
tests for a BBX2(s) and MCC(s). All measurements are made through
the appropriate RX output connector using the calibrated RX cable
setup.
Refer to Table 4-2 to perform an all-inclusive RX ATP test on selected
devices.
Prerequisites
Before attempting to run any ATP tests, ensure the following have been
completed:
CSMs, GLI2s, BBX2s, and MCCs have correct code load and data
load
Primary CSM, GLI2, and MCCs are INS
BTS has been Optimized/Calibrated
BBX2s are OOS–RAM
Test equipment is connected for ATP tests (see Figure 3-16 through
Figure 3-19).
Test equipment is warmed up 60 minutes and calibrated
Test cables are calibrated
GPIB is on
LMF is logged into the BTS