User Manual

Automated Acceptance Test Procedure – All-Inclusive TX & RX – continued
July 1999
4-3
SC 4812ET BTS Optimization/ATP – CDMA LMF
PRELIMINARY 2
Prerequisites
Before attempting to run any ATP tests, ensure the following have been
completed:
CSMs, GLI2s, BBX2s, and MCCs have correct code load and data
load
Primary CSM, GLI2, and MCCs are INS
BTS has been Optimized/Calibrated
BBX2s are OOS–RAM
Test equipment is connected for ATP tests (see Figure 3-16 through
Figure 3-19).
Test equipment is warmed up 60 minutes and calibrated
Test cables are calibrated
GPIB is on
LMF is logged into the BTS
Table 4-1: All TX Acceptance Test
Step Action
1 Select the BBX2(s) and MCC(s) to be tested.
2 From the Tests menu, select All TX
3 Select the appropriate carrier(s) (carrier – bts# – sector# – carrier#) displayed in the
Channels/Carrier pick list (use the Shift or Ctrl keyboard key to select multiple items).
4 Type the appropriate channel number in the Carrier n Channels box.
5 Click OK.
6 Follow the cable connection directions as they are displayed.
7 Click OK to close the status report window.
4