User Manual

Automated Acceptance Test Procedure – All–inclusive TX & RX – continued
PRELIMINARY 2
SC 4812ET BTS Optimization/ATP – CDMA LMF
July 1999
4-2
ATP Tests Prerequisites
Before attempting to run any ATP tests, ensure the following have been
completed:
CSMs, GLI2s, BBX2s, and MCCs have correct code load and data
load
Primary CSM, GLI2, and MCCs are INS
BTS has been optimized and calibrated
BBX2s are OOS-RAM.
BBX2s are calibrated and BLOs are downloaded
Test equipment has been warmed up 60 minutes and calibrated
Test cables are calibrated
GPIB is on
LMF is logged into the BTS
TX/RX OUT Connections
Many of the acceptance test procedures require taking
measurements at the TX OUT (BTS/RFDS) connector. At
sites with RFDS, all measurements are through the RFDS
directional coupler TX OUT connector.
IMPORTANT
*
Figure 4-1F shows the TX/RX connector configuration for the SC
4812ET frame.
Figure 4-1: TX/RX Connections
All TX ATP Test
Table 4-1 lists the procedure to execute the TX Mask, Rho, PtOffset, and
Code Domain Power tests. This procedure eliminates the need to run
separate tests and reduces test time.
The LMF Tests menu list item, All TX, performs all transmit tests for a
BBX2(s).
If manual testing with the HP analyzer, remove the manual
control/system memory card from the card slot before
starting the automated testing.
IMPORTANT
*
4