RFDS Setup and Calibration – continued
PRELIMINARY 2
SC 4812ET BTS Optimization/ATP – CDMA LMF
July 1999
3-76
Program TSU NAM
The Program TSU NAM option allows for the entry of TSU
programming data.
Prerequisite
Ensure that the following has been completed prior to programming the
TSU NAM:
MGLI is INS.
TSU is powered up and has a code load.
Program TSU NAM
Follow the procedure in Table 3-44 to program the TSU NAM. The
NAM must be programmed before it can receive and process test calls,
or be used for any type of RFDS test.
Prerequisites
MGLI is INS.
TSU is powered up and has a code load.
Table 3-44: Program NAM Procedure
Step Action
1 Select the RFDS.
2 Select the TSU.
3 Click on the TSU menu.
4 Click on the Program TSU NAM menu item.
5 Enter the appropriate information in the boxes (see
Table 3-42 and Table 3-43) .
6 Click on the OK button to display the status report.
7 Click on the OK button to close the status report window.