Installation Manual

Table Of Contents
T asks 10 -13: Connecting RGPS , Spans, Customer Alarms Chapter 2: UBS Macro B T S Installation Procedure
Tasks 10 -13: Connecting RGPS, Spans, Customer
Alarms
Objectives
The S SI pro vides only secondary surge protection for the RGPS and T1/E1 span
connections. The customer is responsible for pro viding primary surge protection.
The objectives of performing T asks 10–13 are as follows:
Install RGPS cable (AA) between the RGPS cable lightning arrester and the UBS Macro
BTS .
Install T1/E1 balanced Span I/O cable (W) between the UBS Macro BTS and the site span
line interconnect equipment.
Install E1 unbalanced Span I/O coaxial cables (customer supplied) between the UBS Macro
BTS and the site span line interconnect equipment.
Install Customer Alarm Input/Output (IP/OP) cables (X) between the UBS Macro BTS and
the Customer IP/OP interconnect equipment.
The site configuration/characteristics determines whether the cables in T asks 10 -13 are to be
installed.
Cabling options
The site characteristics determine the use of cables AA, W and X.
The RGPS cable (AA) is optional and used only when the optional RGPS head is used.
The T1/E1 balanced Span I/O cable (W) can carry up to 8 spans, but the UBS Macro BTS
currently supports only up to 4 spans. This is also true for E1 unbalanced Span I/O coaxial
cables (customer supplied).
F or Span I/O cable (W), the minimum size of span line wires is 26 A WG .
The usage and quantity of Customer Alarm Input/Output (IP/OP) cables (X) is determined by the
customer .
2 -46 68P09283A62 -3