Installation Manual

Table Of Contents
R20 1X UBS Macro B T S Hardw are Installation Full installation sequence
Full installation sequence
Overview
The installation of the UBS Macro BTS is composed of two parts to be performed in this order:
1. V erifying site and equipment
2. Physical installation
Once the site is verified, the BTS can be physically installed.
Details to perform each part are given here along with any prerequisites.
Prerequisites
This document is not a planning guide and is not meant to provide planning information. All site
planning, including power requirements and installation of site power , must be completed before
performing the installation. The site verification will help verify this prerequisite has been met.
A Structural Engineer has been consulted and has determined the method to mount the rack to
the floor .
Verifying site and equipment
This can be performed at any time prior to the physical installation. V erifying site and equipment
is composed of two portions to be performed in this order:
1. Site verifications - Refer to Site verification on page 2 - 15 to verify the site.
2. Unpack and identify the equipment - Refer to Unpacking Instructions on page 1 - 18 and
unpack the various cartons. Refer to Figure 1 -6 and verify the correct equipment is
present. The exact number and type of equipment is site dependent.
Physical installation
Recommendations
Motorola recommends performing the physical installation all at once and not in multiple stages.
Motorola recommends installing cable ties to eliminate confusion and clutter .
68P09283A62 -3 2 -11
PRELIMINARY A UG 2007