T est Set Calibr ation Chapter 3: LMF Oper ation
Zero Out Power Meter
Before using the MT8212B test set to perform RF power measurement, the test set internal
power meter function must be zeroed.
Prerequisites The following must be done before the zeroing out the power meter:
The test set is connected to the LMF computer serial port with the
Anritsu
800 -441 RS -232
serial interface cable
T est equipment is turned on and has warmed up for at least 60 minutes.
T est equipment has been selected/detected in the LMF ( T est Equipment Selection on
page 3 - 48 )
Zero out power meter P erform the following to zero out the power meter function before
performing RF power measurements.
Procedure 3 -15 Anritsu MT8212B Multi -function T est Set Z ero Out P ower Meter
1
In the LMF menu bar select Util > Calibrate T est Equipment .
Result: A Calibrate
Anritsu
MT8212B window appears.
2
Click in the Option for zero out power meter on
Anritsu
MT8212B radio button in
the Zero Out P ower Meter area.
Result: A black dot appears in the circle.
3
Click on OK .
Result: A Directions window is displayed.
4
F ollow the directions provided.
Result: A status report window will open.
5
Click on OK to close the status report window .
Calibrate TX Analyzer
TX Analyzer calibration should be accomplished before performing any A TP operations with
the MT8212B.
Prerequisites The following must be done before the CW generator calibration:
The test set is connected to the LMF computer serial port with the
Anritsu
800 -441 RS -232
serial interface cable
T est equipment has been selected/detected in the LMF ( T est Equipment Selection on
page 3 - 48 )
Additional items must be available for the TX Analyzer calibration method chosen as
indicated in the following:
3 -58 68P09283A63 -5