Installation Manual

T asks 2 -3: Installing R ack & Ground Cable Chapter 2: UBS Macro B T S Installation Procedure
Tasks 2 -3: Installing Rack & Ground Cable
Objectives
The objectives of this procedure are as follows:
Mount the rack to the floor .
Install the ground cable (DD).
Rack requirements
The UBS Macro BTS equipment is designed to be mounted in an open standard 19–inch rack.
T o ensure proper equipment support, grounding, and easy installation, Motorola recommends
that the UBS Macro BTS equipment be mounted in one of the following applicable Motorola
racks:
STHN4120 19–inch (1800 mm)
STHN4121 19–inch (1400 mm)
STHN4122 19–inch (1000 mm)
Structural engineer prerequisite
Ensure that the procedure, tools, and equipment required to mount the rack to the floor are
specified by a Structural Engineer .
2 -28 68P09283A62 -3
PRELIMINARY A UG 2007