User Manual

1X UBS Macro B T S Optimization/A TP Scope and La y out
Intended Reader Prole
The information in this manual set is intended for use by cellular communications personnel in
the initial installation and configuration, as well as the day -to -day operation and maintenance
of a UBS .
The user of this information must have a general understanding of telephony , as used in the
operation of the Public Switched T elephone Network (PSTN), and must be familiar with these
concepts as they are applied in the cellular and mobile/portable radio telephone maintenance
environment.
The user also must have a working knowledge of W indows 2000 or W indows XP™.
Publication Composition
This publication covers the following areas.
Introduction: preliminary background information (such as component and subassembly
locations and UBS layouts) to be considered by the Cellular Field Engineer (CFE) before
optimization or tests are performed.
Preliminary Operations: UBS subassemblies, pre–power up tests, initial power application,
and power–up tests for the UBS after installation.
Optimization: code syncing all UBS processor boards, test equipment setup and calibration,
UBS verification, radio frequency (RF) path verification, and RF calibration as necessary .
Field V erification: A t the site the UBS is assembled per the installation manual and tested
using TX Audit and RS SI procedures.
Acceptance T est Procedures (A TP): automated A TP scripts executed by the LMF and used
to verify all major transmit (TX) and receive (RX) performance characteristics on all UBS
equipment. Includes generating an A TP report. Using the full A TP is optional.
Prepare to Leave the Site: site turnover process after A TP is completed.
Basic Troubleshooting: procedures to perform when an A TP fails, as well as when incorrect
results are obtained during logon, test equipment operation, audit, and Global P ositioning
System (GPS) operation. These tests are typically used to isolate faults down to the module
level. Also provided is additional information necessary to better understand equipment
operation.
Appendices containing data sheets to be filled out manually by the CFE at the site,
optimization/A TP matrix, output power data tables, CDMA operating frequency
programming information, and manual test setup information. .
68P09283A63 -5 1 -3
FOA A UG 2007