Installation Instructions

Installation completion Chapter 4: What s Next
Installation completion
A t this point the hardware installation is complete. P erform the following tasks to complete the
system installation.
Clean up the site
Fill out the installation completion checklist
Record As -Built information
P erform the A TP s
Load the software
P erform the clean up of the site and fill out the checklist, first. Then perform the rest of the
tasks or perform them later .
Clean up the site
Clean up the site by following the instructions given in Procedure 4 -1 .
Procedure 4 -1 Cleaning the site
1
Remove protective covering
Remove any cardboard from the walls that was used to protect the walls.
Remove any antistatic plastic or cloth sheet used to cover the equipment.
2
Lighting fixtures
Remove any masking tape from the fluorescent light fixtures.
3
T ools
Place all hand and power tools in the installation tool kit or other appropriate
place. Check for any tools requiring replacement, cleaning, or adjustment.
4
Materials
Place any leftover materials in a location specified by the site manager .
5
Remove debris
T o remove the debris, perform the following:
Remove any packing material.
Ensure that all scrap materials are removed from any tables or stands.
Clean/sweep the floor . Ensure all chalk -line marks are removed.
Continued
4 -2 68P09283A62 -3
PRELIMINARY A UG 2007