User's Manual

Test Equipment Set-up
68P09258A31–A
Oct 2003
1X SCt 4812T BTS Optimization/ATP
3-60
Equipment Warm-up
NOTE
To assure BTS stability and contribute to optimization accuracy
of the BTS, warm-up the BTS test equipment prior to
performing the BTS optimization procedure as follows:
Agilent E7495A for a minimum of 30 minutes
All other test sets for a minimum of 60 minutes
Time spent running initial or normal power-up, hardware/
firmware audit, and BTS download counts as warm-up time.
WARNING
Before installing any test equipment directly to any BTS TX
OUT connector, verify there are no CDMA channels keyed.
At active sites, have the OMC-R/CBSC place the antenna
(sector) assigned to the LPA under test OOS. Failure to do
so can result in serious personal injury and/or equipment
damage.
Automatic Cable Calibration Set–up
Figure 3-12 through Figure 3-15 show the cable calibration setup for
various supported test sets. The left side of the diagram depicts the
location of the input and output ports of each test set, and the right side
details the set up for each test.
Manual Cable Calibration
If manual cable calibration is required, refer to the procedures in
Appendix F.
3