User's Manual

Automated Acceptance Test Procedures
68P09258A31–A
Oct 2003
1X SCt 4812T BTS Optimization/ATP
4-2
Automated Acceptance Test Procedures
Introduction
The Automated Acceptance Test Procedure (ATP) allows Cellular Field
Engineers (CFEs) to run automated acceptance tests on all equipped BTS
subsystem devices using the Local Maintenance Facility (LMF) and
supported test equipment per the current Cell Site Data File (CDF)
assignment.
The results of these tests (at the option of the operator) are written to a
file that can be printed. All tests are controlled from the LMF platform
using the GPIB interface, therefore, only recommended test equipment
supported by the LMF can be used.
This chapter describes the tests run from the GUI environment, which is
the recommended method. The GUI provides the advantages of
simplifying the LMF user interface, reducing the potential for miskeying
commmands and associated parameters, and speeding up the execution
of complex operations involving multiple command strings. If you feel
the command line interface (CLI) will provide additional insight into the
progress of ATPs and problems that could possibly be encountered, refer
to LMF CLI Commands.
NOTE
Before performing any tests, use an editor to view the
“Caveats” section of the “readme.txt” file in the c:\wlmf
folder for any applicable information.
The ATP test is to be performed on out-of-service (OOS)
sectors only.
DO NOT substitute test equipment not supported by the
LMF.
Refer to Chapter 3 for detailed interconnection information needed for
calibrating equipment, cables, and other test equipment set components.
4