User's Manual Part 4
New Packet BTS Installation with IBR – continued
MAY 2004 1X SC480 BTS Hardware Installation, Optimization/ATP, and FRU H-3
PRELIMINARY
Table H-1: Implement IBR Functionality in New BTS
Step Action
7 Refer to the site documentation for IBR spans and inspect the BTS span cabling connections to be sure
they match Figure H-1.
8 Correct any cabling discrepancies between the BTS span cabling and site documentation, referring to
Figure H-1 and the Install Span and Alarm Cables and Span Line Cable Pin Numbering Chapter 4 of
this manual as required.
9 If the BTS requires optimization and/or ATP, perform them at this time by following the applicable
procedures in Chapter 6 of this manual.
10 When all preparations for BTS operation are completed, contact the OMC–R and notify the operator
that the BTS is ready for operation and request notification when the operator no longer requires
support on–site.
11 When advised that there is no further requirement for on–site support of BTS and IBR initialization,
proceed to Chapter 8 and follow the procedures to prepare to leave the site.
H