User's Manual Part 4

Logical BTS LAN Configuration for Compact BTS (Indoor) – continued
MAY 2004 1X SC480 BTS Hardware Installation, Optimization/ATP, and FRU F-3
PRELIMINARY
Logical BTS LAN Cabling
Installation Procedure
Follow the procedure in Table F-1 for installation of LAN cables for
Logical BTS.
Table F-1: Procedure for Installing LAN Cabling for Logical BTS
Step Action
1 Follow the procedure in Chapter 4 for installing a Compact BTS in a rack.
2 For a 3 BTS expansion configuration, follow Figure F-1. Proceed to step 3.
2a For a 2 BTS expansion configuration, follow Figure F-2. Proceed to step 3.
2b For a 1 BTS expansion configuration, follow Figure F-3. Proceed to step 3.
3 Route LAN cables through conduit from Starter to Expansion BTS 1.
4 Route LAN cables through conduit from Starter to Expansion BTS 2 or 3 (depending on
configuration).
5 If in use, route LAN cables from Expansion BTS 1 to Expansion BTS 2.
6 If in use, route LAN cables from Expansion BTS 2 to Expansion BTS 3.
7 Ensure that unused LAN connections are terminated in 50 ohms.
8 If not already performed, proceed to Appendix E for expansion cabling diagrams.
9 Perform Optimization and ATP as described in Chapter 6. LMF Help provides further information.
F