User's Manual Part 2
AC Power Input (Outdoor Configuration) – continued
5-8 1X SC480 BTS Hardware Installation, Optimization/ATP, and FRU MAY 2004
PRELIMINARY
Table 5-7: PDE Initial Power –Up Test
Step Action
7 Using a DMM set toVAC, measure the voltage at the AC terminal block. DMM should indicate
200–240 VAC. Adjust AC voltage as necessary.
8 Remove DMM.
9 If there is nothing further to do, replace safety shield. Secure to cabinet with 2 nuts and washers. Use
an adjustable wrench to tighten nuts. Torque nuts to 3.4 N–M (20 in–lbs).