User's Manual Part 2

Preliminary Operations: Overview
MAY 2004
1X SC480 BTS Hardware Installation, Optimization/ATP, and FRU
PRELIMINARY
6-2
S Effective Rate Power (ERP) table for all TX channels to antennas
respectively. Motorola System Engineering specifies the ERP of a
transmit antenna based on the site geography, antenna placement, and
government regulations. Working from this ERP requirement, the
antenna gain, (dependent on the units of measurement specified) and
antenna feed line loss can be combined to determine the required
power of the BTS. The corresponding BBX–1X output level required
to achieve that power level on any channel/sector can also be
determined.
Refer to the LMF Help function on–line documentation for
additional information on the layout of the LMF directory
structure (including CDF or NEC file locations and
formats).
NOTE
Site Equipage Verification
Review the site documentation. Match the site engineering equipage data
to the actual boards and modules shipped to the site. Physically inspect
and verify the equipment provided for the frame.
Always wear an approved anti–static wrist strap while
handling any circuit card/module to prevent damage by
ESD. After removal, the card/module should be placed on
a conductive surface or back into the anti–static packaging
in which it was shipped.
CAUTION
Initial Installation of
Boards/Modules
Table 6-1: Initial Installation of Boards/Modules
Step Action
1 Refer to the site documentation and, if it was not previously done, slide all boards and modules into
the appropriate shelves as required. DO NOT SEAT the boards and modules at this time.
2 As the actual site hardware is installed, record the serial number of each module on a “Serial Number
Checklist” in the site logbook.
6